Mount Henry Bridge

From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Paul Fisher (talk | contribs) at 05:04, 23 July 2006 (Article initiated). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

The Mount Henry Bridge carries the Kwinana Freeway over the Canning River in Perth, Western Australia, approximately 10 kilometres south of te Perth central business district.

History

The bridge was constructed as part of the extension of the Kwinana Freeway carried out in the late 1970s and early 1980s. The bridge was opened in 1982. The construction contractor was Clough, and the project manager for Main Roads WA was Geoff Smith.

Between 2004 and 2006, the Mount Henry Bridge was widened and strengthened to accommodate the tracks of the Perth Southern Suburbs Railway. The widening was carried out by adding a structurally independent structure, which overlaps the original bridge.

Mount Henry Bridge

Structural details

The original bridge is of post-tensioned concrete. It has nine spans with a total length of 660 metres. The deck width is 28.8 metres. In cross section it is a double box-section, with the upper deck (including cantilevers) carrying traffic, and cantilevers at the bottom of the box carrying pedestrian / cycle paths. The bridge was constructed segmentally, using a balanced caltilever construction method. The original bridge carried three lanes of traffic in each direction, with two pedestrian / cycle paths on cantilevers at the lower lever.

Widening and strengthening

To accommodate the new Southern Suburbs Railway, the bridge was widened and strengthened between 2004 and 2006. Under the new arrangement, the original bridge carries three southbound traffic lanes and the two railway tracks. The new structure carries the three northbound traffic lanes.

Because of the aesthetic requirements, load limitations and limited site space at the approaches, the new bridge overlaps the original in cross section. The upper east side cantilever sits above the upper west side cantilever of the original structure, giving a total effective deck width of 40 metres. The foundations of the new bridge are independent of the original, with each pier comprising two columns tapering from bottom to top.

The new bridge was constructed by incremental launching. Contractors were Leighton Constructions. The design team comprised Wyche Consultants, GHD and Coffey Geosciences.


Some statistics