Gas network access ordinance

from Wikipedia, the free encyclopedia
Basic data
Title: Ordinance on access to gas supply networks
Short title: Gas network access ordinance
Abbreviation: GasNZV
Type: Federal Ordinance
Scope: Federal Republic of Germany
Issued on the basis of: Sections 21b, 24, 25, 29 EnWG
Legal matter: Commercial administrative law , energy law
References : 752-6-13
Original version from: July 25, 2005
( BGBl. I p. 2210 )
Entry into force on: July 29, 2005
Last revision from: September 3, 2010
( BGBl. I p. 1261 )
Entry into force of the
new version on:
September 9, 2010
Last change by: Art. 1 Regulation of 13 June 2019
( Federal Law Gazette I, p. 786 )
Effective date of the
last change:
June 20, 2019
(Art. 3 of June 13, 2019)
Please note the note on the applicable legal version.

The Gas Network Access Ordinance is an implementation ordinance for the Energy Industry Act for the liberalization of the gas market in Germany . This regulates the opening of the gas market in Germany.

Main point of content

The main difficulty in opening up the gas market was the procedure when an end customer changed supplier. This is regulated in Section 37 GasNZV. This regulates on the one hand by when the gas industry must have developed a procedure and on the other hand by when it must be implemented in a computer platform.

Time schedule

Lt. Section 37 (1) sentence 1 GasNZV must

  • by February 1, 2006 the procedure will be fully developed.
  • by August 1, 2006 the process must be implemented in a computer platform.

According to Section 37 (1) sentence 3 GasNZV, both dates can be extended by up to 6 months after approval by the Federal Network Agency . In fact, an extension of 2 months was granted.

The actual opening of the gas market took place on the following dates:

  • The process had to be fully developed by April 1, 2006. From this time on, third-party providers could change suppliers. Since a platform is not available, this would have to be done manually. At best, this would be worthwhile for large customers.
  • The platform had to be in place by October 1, 2006. From then on, the market will also be able to open up to small private customers.