Data
Type Biogas plant with biogas processing
Primary energy Biomass (especially maize)
power 50 MW th
operator NAWARO BioEnergie AG
Start of operations 2009
Website www.nawaro.ag
f2

The BioEnergie Park Güstrow is the world's largest biogas plant . The plant is operated by NAWARO BioEnergie AG and is located north of the city of Güstrow in Mecklenburg-Western Pomerania .

Plant details

The plant consists of a total of 20 fermenters , each with a capacity of 5,000 t. Downstream of the fermenters is a biogas treatment system that feeds 5,000 cubic meters per hour or 43 to 46 million cubic meters per year of biomethane (corresponding to an energy of approx. 50  GWh ) into the 25-bar natural gas network. 400,000 t of substrate are required annually . The main substrate used is maize , but also whole- crop silage , grain and grass silage . 80,000 t of substrate can be stored in an interim storage facility consisting of several silos.

Literature and Sources

  • Gerd Rinas: Under full load . Almost a year after commissioning, Nawaro BioEnergie Park Güstrow reaches the planned production capacity / the world's largest biogas plant generates 43 million m³ of bio natural gas per year / 70 farmers supply substrate. In: BauernZeitung . No. 20 , 2010 ( online as PDF , 1.53 MiB [accessed October 7, 2012]).
  • BioEnergie Park Güstrow. NAWARO BioEnergie AG, accessed on October 7, 2012 .
  • Guestrow. Plant profile. In: Biogas partner. Deutsche Energie-Agentur GmbH (dena), accessed on October 7, 2012 .

Web links

Commons : BioEnergie Park Güstrow  - Collection of images, videos and audio files