Lock type: | double curved arch dam | ||||||||||
Construction time: | 2002-2009 | ||||||||||
Height above valley floor: | 210 m | ||||||||||
Building volume: | 272 000 m³ | ||||||||||
Crown length: | 132 m | ||||||||||
Crown width: | 7 m | ||||||||||
Base width: | 25 m | ||||||||||
Power plant output: | 306.5 MW | ||||||||||
Operator: | Devlet Su İşleri (DSİ) | ||||||||||
Data on the reservoir | |||||||||||
Altitude (at congestion destination ) | 694 m | ||||||||||
Water surface | 58.74 km² | ||||||||||
Reservoir length | 27.3 km | ||||||||||
Storage space | 4582 million m³ |
The Ermenek Dam ( Turkish Ermenek Barajı ) is a dam in southern Turkey . It was built by the Turkish Water Management Authority near Ermenek on the Ermenek Çayı , a tributary of the Göksu .
The barrier structure is a double-curved concrete arch dam with a height of 210 m and a length of 132 m. The hydropower plant has two Francis turbines with an output of 306 MW and provides 1048 GWh of electricity per year. In August 2009, the construction work was so far completed that the reservoir has been dammed since then . The opening ceremony took place in December 2009. Downstream is the Gezende Dam .
See also
- List of the largest dams on earth
- List of the largest reservoirs on earth
- List of the largest hydroelectric plants in the world
- List of dams in the world
Web links
- Directory of the Turkish hydraulic engineering authority (DSI) ( Memento from February 3, 2010 in the Internet Archive )
- The Ermenek Dam and Hydroelectric Power Plant
- Ermenek Dam & Hydropower Project (PDF file 349 kB)
- Ermenek: WWF Turkey calls for funding to be suspended
- Ermenek Consortium