Połaniec power station
| Połaniec power station | |||
|---|---|---|---|
| location | |||
|
|
|||
| Coordinates | 50 ° 26 '13 " N , 21 ° 20' 13" E | ||
| country |
|
||
| Data | |||
| Type | Thermal power plant | ||
| Primary energy | Fossil energy | ||
| fuel | Hard coal | ||
| power | 1800 MW | ||
| owner | Enea | ||
| operator | Enea | ||
| Start of operations | 1979 | ||
The Połaniec Power Plant is a coal-fired power plant in Połaniec , Świętokrzyskie , Poland . It is owned by Enea and operated by Enea.
owner
In 2017, Enea took over 100% of the shares in ENGIE Energia Polska from Engie , the previous operator of Połaniec.
Power plant units
The power plant consists of a total of 8 units that went into operation from 1979 to 1983. The following table gives an overview:
| block | Max. Power (MW) | Start of operation | turbine | generator | Steam boiler |
|---|---|---|---|---|---|
| 1 | 225 | 1979 | Zamech | Dolmel | Taganrog |
| 2 | 225 | 1980 | Zamech | Dolmel | Taganrog |
| 3 | 225 | 1980 | Zamech | Dolmel | Taganrog |
| 4th | 225 | 1981 | Zamech | Dolmel | Taganrog |
| 5 | 225 | 1981 | Zamech | Dolmel | Taganrog |
| 6th | 225 | 1982 | Zamech | Dolmel | Taganrog |
| 7th | 225 | 1982 | Zamech | Dolmel | Taganrog |
| 8th | 225 | 1983 | Zamech | Dolmel | Taganrog |
Unit 8 was converted from 2010 to 2012 for the combustion of biomass. Up to 890,000 t of wood chips and 220,000 t of agricultural waste are to be used annually. The cost of conversion amounted to 290 million USD .
In 2015, Alstom received the order to modernize blocks 2 to 7. This will increase the output of these units to 240 MW. The order value was € 65 million .
See also
Web links
Commons : Połaniec power station - collection of images, videos and audio files
Individual evidence
- ↑ Enea the owner of Połaniec Power Plant - transaction with ENGIE successfully completed. Enea , March 14, 2017, accessed April 23, 2018 .
- ^ Polaniec Coal Power Plant Poland. Global Energy Observatory, accessed April 23, 2018 .
- ↑ Polaniec Biomass Power Plant. www.power-technology.com, accessed on April 23, 2018 (English).
- ↑ Alstom signs modernization contract worth approximately € 65 million for the Polaniec Power Plant in Poland. (No longer available online.) Alstom , July 22, 2015, archived from the original on May 10, 2017 ; accessed on April 23, 2018 (English). Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice.