Brandberg Tunnel
| Brandberg Tunnel | ||
|---|---|---|
| use | Road tunnel | |
| traffic connection | L330 | |
| place | Mayrhofen | |
| length | 2130 m | |
| cross-section | 70 m² | |
| construction | ||
| Client | Tauernkraftwerke AG | |
| completion | 1976 | |
| location | ||
|
|
||
| Coordinates | ||
| North portal | 47 ° 10 ′ 38 " N , 11 ° 52 ′ 20" E | |
| South portal | 47 ° 9 ′ 38 " N , 11 ° 53 ′ 9" E | |
The Brandberg Tunnel connects the villages of Mayrhofen-Laubichl and Brandberg in the Zillertal . This tunnel takes you from the Zillertal Straße (B 169) to the opposite valley ( Zillergrund ), on the course of the Ziller , without having to drive through the town of Mayrhofen.
The tunnel was originally built as an access to the Zillergründl power plant construction site and therefore has a rather unusual high gradient for road tunnels.