Westermost Rough offshore wind farm

from Wikipedia, the free encyclopedia
Westermost Rough
Westermost Rough Windfarm from Killingholme.jpg
location
Westermost Rough offshore wind farm (North Sea)
Westermost Rough offshore wind farm
Coordinates 53 ° 48 '18 "  N , 0 ° 8' 56"  E Coordinates: 53 ° 48 '18 "  N , 0 ° 8' 56"  E
country United Kingdom
Waters North Sea
Data
Type Offshore wind farm
Primary energy Wind energy
power 210 MW
Start of operations May 2015
founding Monopile
turbine 35 Siemens SWT-6.0-154
was standing August 2016
f2

Westermost Rough is an offshore wind farm in the United Kingdom in the North Sea . The wind farm has an electrical output of 210  megawatts and can supply over 150,000 households with electricity. Its standard work capacity is more than 800  GWh per year. It is located five miles off the coast of Holderness .

construction

The first foundation was installed in February 2014. The wind farm went into operation in May 2015.

technology

Westermost Rough was the first offshore wind farm to use 6-megawatt wind turbines with 75-meter-long rotor blades. 35 Siemens SWT-6.0-154 were installed. The systems are 177 meters high up to the tip of the blade. The monopiles used have a diameter of 6.5 meters and a weight of up to 800 tons.

business

The wind farm is a joint venture owned by DONG Energy (50%), Marubeni Corporation (25%) and the UK Green Investment Bank (25%).

See also

Individual evidence

  1. UK Green Investment Bank invests £ 461m in the UK offshore wind sector. Renewable Energy Focus, April 2, 2014, accessed August 31, 2016 .
  2. a b c Ribbon Cut at Westermost Rough OWF. offshorewind.biz, July 1, 2015, accessed on August 31, 2016 .
  3. a b Smooth start at Westermost Rough. February 25, 2014, accessed August 31, 2016 .
  4. Westermost Rough hits full power. (No longer available online.) Renews.biz, May 26, 2015, archived from the original on May 30, 2015 ; accessed on August 31, 2016 . Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. @1@ 2Template: Webachiv / IABot / renews.biz