Hugenwald tunnel

from Wikipedia, the free encyclopedia
Hugenwald tunnel
Hugenwald tunnel
West portal with rescue tunnel under construction
use Road tunnel
traffic connection Bundesstrasse 294
place Waldkirch
length 1135 m
Number of tubes 1
construction
Client Regional council Freiburg
building-costs 41.9 million DM
start of building 1980
completion 1985
business
toll no
release December 13, 1985
location
Hugenwald tunnel (Baden-Württemberg)
Red pog.svg
Red pog.svg
Coordinates
West portal 48 ° 5 ′ 8 "  N , 7 ° 57 ′ 10"  E
East portal 48 ° 5 ′ 20 "  N , 7 ° 58 ′ 2"  E

The Hugenwald tunnel is a 1135 m long road tunnel in which the B 294 crosses the town of Waldkirch in the Elztal . The two-lane two-way traffic tunnel runs in a west-east direction south of the city.

construction

The first plans for the construction of a bypass tunnel for Waldkirch were made in the 1950s. Surveying work began in 1969, and three planning variants were worked out. The plan approval decision was made in 1977. The tunnel was first opened on September 23, 1980, and the tunnel breakthrough on August 25, 1981. The tunnel was then expanded by 1985. The tunnel was opened on Friday, December 13, 1985 by Dietmar Schlee , then Minister of the Interior and Transport of Baden-Württemberg . At that time the Hugenwald tunnel was the longest single-tube road tunnel in the Federal Republic of Germany.

business

The tunnel is passed by almost 20,000 vehicles every day. The maximum permissible speed in the tunnel is normally 80 km / h. The ventilation takes place as longitudinal ventilation with a central chimney. A little outside the center of the tunnel there is a central cavern with a 60 m high exhaust chimney.

Safety retrofitting and renovation

After two and a half years of renovation for 27 million euros with temporary closure, the Hugenwald tunnel was opened to traffic again in June 2014. In the first construction phase, a 2.25 m wide and high rescue tunnel was built parallel to the main tunnel. Preparatory work for this began in spring 2011. The operating technology was housed in a new tunnel operations building at the east portal north of the B 294. In the second phase, the existing tunnel was renovated.

Others

The six cables (two three-phase circuits ) of the 110 kV double line between the Denzlingen and Bleibach substations are also laid in the tunnel, which among other things supplies the rear Elz Valley with electrical energy.

Individual evidence

  1. "A tunnel for a better quality of life" : Article in the Badische Zeitung of December 13, 2010 on the 25th anniversary of the tunnel opening
  2. Information in the local council about tunnel renovation June 28, 2011 on the current construction planning
  3. Technical information on the tunnel from an engineering office involved in the construction
  4. ^ "First work in the Hugenwald tunnel" (article in the Badische Zeitung from April 19, 2011)
  5. Waldkirch: Hugenwald tunnel is free for traffic again - badische-zeitung.de. Retrieved June 3, 2014 .
  6. ^ "Up-to-date substation" : Badische Zeitung dated June 4, 2009 to convert the second line to 110 kV voltage