Ringhals nuclear power plant

from Wikipedia, the free encyclopedia
Ringhals nuclear power plant
Ringhals nuclear power plant, units 3 and 4
Ringhals nuclear power plant, units 3 and 4
location
Ringhals Nuclear Power Plant (Sweden)
Ringhals nuclear power plant
Coordinates 57 ° 15 ′ 40 "  N , 12 ° 6 ′ 30"  E Coordinates: 57 ° 15 ′ 40 "  N , 12 ° 6 ′ 30"  E
Country: Sweden
Data
Owner: Ring neck AB
Operator: Ring neck AB
Project start: 1968
Commercial operation: Jan. 1, 1976

Active reactors:

3
Energy fed in in 2006: 27,021 GWh
Energy fed in since commissioning: 609,769 GWh
Was standing: July 25, 2007
The data source of the respective entries can be found in the documentation .
f1

The Ringhals nuclear power plant with four reactor blocks, one of which is a boiling water reactor and three pressurized water reactors , is located in the municipality of Varberg , in the southern Swedish province of Halland County .

The nuclear power plant is located on the Värö peninsula (Swedish: Väröhalvön) approx. 60 km south of Gothenburg . With a total installed capacity of 3560  MW , it is the most powerful Swedish nuclear power plant and generates around 24 TWh of electricity per year, which corresponds to 20% of Swedish electricity consumption.

Over 1000 people are employed at the Ringhals nuclear power plant. The operator of the power plant is Ringhals AB , 70.4% of which is owned by Vattenfall and 29.6% by Uniper . The operator announced that it would shut down Unit 1 in 2019 and Unit 2 early in 2020 (previously planned for 2025). Ultimately, however, Block 2 was initially shut down at the end of 2019, and Block 1 is to follow at the end of 2020.

Incidents

Incident in 2006

Shortly after midnight on November 14, 2006, there was an incident in Unit 3 of the nuclear power plant when a fire broke out in one of the two main transformers and then exploded. The reactor shut down quickly and no radioactivity was released, according to authorities . Unit 3 was built from 1972, went into operation in 1981 and has an output of 915 MW.

Ringhals nuclear power plant, block 1 (boiling water reactor, in the background) and 2 (pressurized water reactor)

Operation subject to conditions and official supervision

On July 8, 2009, the Swedish nuclear regulatory authority SSM reported that 60 incidents had already been reported in the power plant in the first half of the year. Two were classified in the highest of three hazard categories. Safety deficiencies that have been complained about by the authorities since 2005 have not been remedied by the operator up to this point in time. The authority expressed fundamental concerns about the necessary security awareness in parts of the group. SSM is placing the power plant under stricter supervision. Vattenfall has to meet special requirements, including regular reporting. The reactor block 1, which was serviced at this point in time, may not be started up again for the time being.

Decommissioning due to serious safety deficiencies

On September 19, 2011, the media reported that in August 2011, as part of renovation work on reactor 2 after the last fire (spring 2011), remains of working material were found in the pipelines of the emergency cooling system. Workers had left them there during welding work in the 1980s. The power plant operator hadn't noticed this deficiency for 30 years. Due to this, all 4 reactors of the power plant were shut down with immediate effect. During the inspection, a sealing ring was also found in reactor 4 within the emergency cooling system. The shutdown applies until the operator has remedied the defects and can explain how this long-term safety risk could arise. On November 13, 2011, the media reported that a vacuum cleaner had been forgotten in reactor 2 during service work in spring. A short circuit in this caused a fire when the reactor was tested. The cleaning work is expected to be completed in December 2011.

Explosives found during routine inspection

During a routine check on June 20, 2012, "civilian explosives" (a fist-sized piece of dough) were found on a forklift truck that was supposed to drive into the innermost security area. Thereupon a search was started and the alertness in this and the other two Swedish nuclear power plants increased by one level.

Data of the reactor blocks

The Ringhals nuclear power plant has a total of four blocks :

Reactor block Reactor type Net power Gross output start of building Network synchronization Commercial operation Shutdown
Ring neck - 1 Boiling water reactor 855 MW 887 MW 02/01/1969 10/14/1974 01/01/1976 Planned for 2020
Ring neck - 2 Pressurized water reactor 867 MW 917 MW 10/01/1970 08/17/1974 05/01/1975 12/30/2019
Ring neck - 3 Pressurized water reactor 985 MW 1037 MW 09/01/1972 07.09.1980 09/09/1981 (approx. 2040)Template: future / in 5 years
Ring neck - 4 Pressurized water reactor 953 MW 979 MW 11/01/1973 06/23/1982 11/21/1983 (approx. 2040)Template: future / in 5 years

See also

Web links

Individual evidence

  1. Decommissioning dates set for Ringhals 1 and 2 October 16, 2015
  2. Press release Nuclear Forum (Switzerland)
  3. Report on DN.se (Swedish)
  4. ^ Spiegel Online: Authority puts Vattenfall nuclear power plant under stricter control
  5. Financial Times Deutschland: Slap in the face from Stockholm for Vattenfall ( Memento from August 4, 2012 in the web archive archive.today )
  6. TAZ online, September 19, 2011
  7. SVT
  8. South Germans discovered explosives on nuclear power plant site (June 20, 2012)
  9. Explosives in the forklift taz (June 22, 2012)
  10. Power Reactor Information System of the IAEA : "Sweden, Kingdom of Power Reactors" (English)
  11. Vattenfall changes the directives for the operating times of Ringhals 1 and 2 Vattenfall Homepage (English; April 28, 2015)
  12. Avveckling av Ringhals 1 och 2 Vattenfall Homepage (Swedish)
  13. Vattenfall: Ringhals nuclear power plant, accessed on December 31, 2019