Verbundnetz (Chile)

from Wikipedia, the free encyclopedia

At present (as of May 2015) there is no nationwide network in Chile , but there are two independent network systems, the Sistema Interconectado Central (SIC) for the center of the country and the Sistema Interconectado del Norte Grande (SING) for the north. In addition, there are various island networks in the south of the country , which are combined in the Sistema Eléctrico de Aysén and in the Sistema Eléctrico de Magallanes .

On April 16, 2015, the Energy Minister of Chile announced that SIC and SING should be synchronized with each other by 2017. The three-phase high-voltage transmission line (500  kV , 1.5  GVA ) to be constructed will be 580 km and 610 km long and cost an estimated US $ 700 and 850 million respectively . The Comisión Nacional de Energía had previously examined 4 different connection options (1 GW or 1,500 GW, DHÜ or HVDC ) in a study.

Sistema Interconectado Central

The SIC or CDEC-SIC ( Spanish Centro de Despacho Económico de Carga del Sistema Interconectado Central ) is the largest network in Chile. It supplies 92% of the population. The installed capacity in the SIC was 15.15 GW at the end of 2014, of which caloric power plants accounted for 7.97 GW (52.6%), hydropower plants 6.4 GW (42%) and wind farms 645.3 MW (4, 26%).

Sistema Interconectado del Norte Grande

The SING or CDEC-SING (Spanish: Centro de Despacho Económico de Carga del Sistema Interconectado del Norte Grande ) is the second network in Chile. The installed capacity in the SING was 4.97 GW at the end of 2014, of which 2.1 GW (42.24%) came from coal-fired power plants and 2.36 GW (47.53%) from gas-fired power plants .

Sistema Eléctrico de Aysén

The Empresa Eléctrica de Aysén SA (Edelaysen) is responsible for electricity generation and distribution in the Región de Aysén . The installed capacity of Edelaysen is 50 MW, mainly consisting of diesel and gas engines.

Sistema Eléctrico de Magallanes

The Empresa Electrica de Magallanes SA (EDELMAG) is in the Magallanes responsible for power generation and distribution. The company operates distribution networks in Punta Arenas , Puerto Natales , Porvenir and Puerto Williams . The installed capacity of EDELMAG is 98.775 MW (or 101 MW), consisting of diesel and gas engines.

Individual evidence

  1. CATASTRO DE CENTRALES Y PROYECTOS ENERGÉTICOS 2012. (PDF 12.8 MB p. 9 (8)) EDITEC SA, accessed on May 1, 2015 (Spanish).
  2. Sistemas Eléctricos. (No longer available online.) EDELMAG, archived from the original on May 18, 2015 ; Retrieved May 1, 2015 (Spanish). Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. @1@ 2Template: Webachiv / IABot / www.edelmag.cl
  3. Ministro de Energía firma Decreto de Interconexión SIC-SING. (No longer available online.) Ministro de Energía, April 16, 2015, archived from the original on May 6, 2015 ; Retrieved May 1, 2015 (Spanish). Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. @1@ 2Template: Webachiv / IABot / www.minenergia.cl
  4. a b Línea de Transmisión Interconexión SING-SIC. BNamericas, archived from the original on March 4, 2016 ; Retrieved May 1, 2015 (Spanish).
  5. ^ Sigdo Koppers construirá interconexión SIC-SING y busca potenciar área de energía. Sociedad de Fomento Fabril (SOFOFA), April 20, 2015, accessed May 1, 2015 (Spanish).
  6. ANALISIS TÉCNICO Y ECONÓMICO DE UNA INTERCONEXIÓN SING-SIC. (PDF 1.6 MB pp. 10–15) (No longer available online.) Comisión Nacional de Energía, March 2012, archived from the original on May 18, 2015 ; Retrieved May 1, 2015 (Spanish). Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice.  @1@ 2Template: Webachiv / IABot / www.cne.gob.cl
  7. Sobre el CDECSIC. (No longer available online.) CDEC SIC, archived from the original on April 24, 2015 ; Retrieved May 1, 2015 (Spanish). Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice.  @1@ 2Template: Webachiv / IABot / www.cdecsic.cl
  8. CDEC SIC public resultados de la operación del Sistema Interconectado Central durante Noviembre de 2014. (No longer available online.) CDEC SIC, archived from the original on May 18, 2015 ; Retrieved May 1, 2015 (Spanish). Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice.  @1@ 2Template: Webachiv / IABot / www.cdecsic.cl
  9. Capacidad Instalada por Combustible Periodo 2006–2015. (No longer available online.) CDEC SING, archived from the original on May 18, 2015 ; Retrieved May 1, 2015 (Spanish). Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. @1@ 2Template: Webachiv / IABot / cdec2.cdec-sing.cl
  10. Empresa Eléctrica de Aysén SA (No longer available online.) BNamericas, archived from the original on May 18, 2015 ; Retrieved May 1, 2015 (Spanish). Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. @1@ 2Template: Webachiv / IABot / www.bnamericas.com
  11. ^ Aysén installed capacity. www.centralenergia.cl, accessed on May 1, 2015 (Spanish).
  12. ^ Identificación Sociedad. (No longer available online.) Empresa Eléctrica de Magallanes SA (EDELMAG), archived from the original on May 18, 2015 ; Retrieved May 1, 2015 (Spanish). Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. @1@ 2Template: Webachiv / IABot / www.edelmag.cl
  13. Sistema de Magallanes. (No longer available online.) EDELMAG, archived from the original on May 18, 2015 ; Retrieved May 1, 2015 (Spanish). Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. @1@ 2Template: Webachiv / IABot / www.edelmag.cl
  14. Historia. (No longer available online.) EDELMAG, archived from the original on January 11, 2015 ; Retrieved May 1, 2015 (Spanish). Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. @1@ 2Template: Webachiv / IABot / www.edelmag.cl
  15. Magallanes installed capacity. www.centralenergia.cl, accessed on May 1, 2015 (Spanish).