Višňové tunnel

from Wikipedia, the free encyclopedia
Višňové tunnel
Višňové tunnel
Construction progress on the west portal, status May 2015
Official name Tunel Višňové
use Motorway tunnel
traffic connection Diaľnica D1
place Višňové / Dubná Skala ( Vrútky )
length 7520 m
Number of tubes 2
construction
start of building 17th June 2014
completion probably 2023Template: future / in 3 years
location
Višňové tunnel (Slovakia)
Red pog.svg
Red pog.svg
Coordinates
West portal 49 ° 9 ′ 3 ″  N , 18 ° 47 ′ 29 ″  E
East portal 49 ° 8 ′ 4 ″  N , 18 ° 53 ′ 18 ″  E

The Višňové Tunnel ( Slovak Tunel Višňové ) is a motorway tunnel under construction in northern Slovakia , which will be built as part of the D1 motorway , section Lietavská Lúčka –Dubná Skala (11.3 km). With its length of 7,520 meters, the tunnel will be the longest engineering structure on the D1 and is expected to be completed in 2023. Two tubes are built from the start. According to current plans, a longer tunnel is planned, the Karpaty tunnel near Bratislava on the D4 motorway with a length of around 9 km.

description

The tunnel will cross the Lúčanská Fatra massif , part of the Little Fatra . The west portal can be found southeast of the center of Višňové and west of the Hoblík mountain ( 933.6  m nm ), the east portal is a few hundred meters southeast of the Dubná Skala quarry, part of the town of Vrútky , immediately before the Dubná Skala junction (km 212 ). The ventilation shaft is located around 1,800 meters from the west portal.

history

East portal in August 2012, construction of the Dubná Skala junction in the foreground

Plans for a tunnel below the Little Fatra have existed since the 1960s, but steps towards the construction of the structure were not taken until the 1990s. The construction of the exploratory tunnel began in September 1998 after the laying of the foundation stone by both portals at the same time. From Višňové a new Austrian tunneling method (NÖT) was used , from Dubná Skala a tunnel boring machine type TBM ATB 35 HA was used. This project was completed on August 24, 2002: a total of 7,480 meters long exploratory tunnel was drilled, of which 3,118 meters are on the west and 4,362 meters on the east side.

According to initial planning, construction of the affected section of the motorway should begin in 2003, but the start of construction has been postponed several times, mostly for financial reasons. Another "official start of construction" took place in February 2010 after the laying of the foundation stone by then Minister of Transport Ľubomír Vážny as part of the PPP project. At that time, completion was expected in the first half of 2014, but after a change of government, PPP projects that had not yet started were canceled.

The public competition for the Lietavská Lúčka – Dubná Skala section began in December 2011, but was delayed by several appeals and appeals. It was only in June 2014 that a construction contract worth 410 million euros (excluding VAT) was signed with the consortium of the Italian construction company Salini Impregilo and the Slovakian Dúha as, which provides for a construction period of 66 months until December 2019. This time, the third laying of the foundation stone took place on June 17, 2014, the drilling officially began on June 9, 2015 with a ceremony. The exploratory tunnel between the two tunnel tubes will be retained for the purpose of drainage.

The breakthrough of the first tube took place on August 28, 2018, that of the second tube followed in the first week of September. Contrary to the original plan, work was delayed by nine months. According to the current status (September 2018), the work should last until 2022.

The following table summarizes the progress in drilling both tunnel tubes (sources: and):

As of ... North tube west portal North tube east portal South tube west portal South tube east portal
February 16, 2016 660 m 484 m 410 m 322 m
5th April 2016 798 m 627 m 636 m 452 m
August 24, 2016 1263.29 m 1395.60 m 1133.16 m 1162.63 m
15th February 2017 1693 m 2232 m 1538 m 1947 m
March 10, 2018 2791.76 m 3640.04 m 2602.94 m 3618.47 m
All in all 6431.8 m 6221.41 m

Individual evidence

  1. Tunel Višňové , dialnice.szm.com of December 22, 2013, accessed on June 21, 2014 (Slovak).
  2. Do tretice všetko dobré, opäť sa začína stavať tunel Višňové , Webnoviny.sk on June 17, 2014, accessed on June 21, 2014 (in Slovak).
  3. Tunel Višňové dostal tretiu šancu , Pravda on June 17, 2014, accessed on June 21, 2014 (Slovak).
  4. Odštartovala výstavba tunela Višňové: Zoznánte sa s náročným projektom v zaujímavých číslach… , Žilina24.sk, accessed on June 9, 2015 (Slovak)
  5. Po dlhom čakaní prišiel prvý výsledok. Najdlhší tunel na Slovensku konečne prerazili Po dlhom čakaní prišiel prvý výsledok. Najdlhší tunel na Slovensku konečne prerazili , hnonline.sk from August 28, 2018, accessed on September 14, 2018
  6. Diaľničný tunel Višňové je prerazený , Pravda on September 14, 2018, accessed on September 14, 2018
  7. Tunel Višňové začiatkom apríla. dated April 11, 2016, zilinskedialnice.sk (Slovak), accessed on August 27, 2016
  8. Aktuálne dianie - Tunel Višňové from August 24, 2016, zilinskedialnice.sk (Slovak), accessed on August 27, 2016
  9. Tunel Višňové a jeho stav vo februári. dated February 18, 2017, accessed July 8, 2017
  10. Tunel Višňové v marci 2018 of March 25, 2018, accessed on September 14, 2018

Web links

Commons : Višňové tunnel  - collection of images, videos and audio files