Arniberg power plant

from Wikipedia, the free encyclopedia
Arniberg power plant
View from the right side of the Reuss valley above Amsteg to the headquarters and the pressure line of the Arniberg power plant.  The arrow indicates the approximate location of Lake Arni.
View from the right side of the Reuss valley above Amsteg to the headquarters and the pressure line of the Arniberg power plant. The arrow indicates the approximate location of Lake Arni .
location
Arniberg power plant (canton Uri)
Arniberg power plant
Coordinates 693827 Price  /  180.56 thousand coordinates: 46 ° 46 '11 "  N , 8 ° 40' 1"  O ; CH1903:  693827 Price  /  180560
country SwitzerlandSwitzerland Switzerland
Canton of UriCanton of Uri Uri
place Gurtnellen municipality
across from Amsteg
Waters Intschialpbach, Leutschachbach, Arnibach
Height upstream 517  m above sea level M.
power plant
owner Elektrizitätswerk Altdorf AG (EWA)
Start of planning 1907
Start of operation 1910
1969 (after renovation)
technology
Bottleneck performance 13 megawatts
Average
height of fall
858 m
Expansion flow 1.8 m³ / s
Standard work capacity 47.22 million kWh / year
Turbines 1910: 2 × Pelton turbines
1912: 3 × Pelton turbines
1969: 2 × Pelton turbines
Generators 1910:
2 × synchronous generator Alioth
1 × synchronous generator BBC
1912:
2 × synchronous generator Alioth
2 × synchronous generator BBC
1969:
2 × synchronous generator
Others
Website EWA power plants
was standing 2018

The power plant Arniberg is a high pressure - hydropower plant in the field of Swiss Municipality Gurtnellen that the Arnisee used as storage week.

The head office of the power plant is located opposite Amsteg and discharges the water into the Reuss . The plant is operated by Elektrizitätswerk Altdorf AG , in which the CKW Group has a stake. The plant was put into operation in 1910 and was a pioneering achievement in European power plant construction due to the extraordinary drop height of 858 m.

history

At the beginning of the 20th century, the Altdorf power station was no longer satisfied with the production of its own Bürglen power station and was looking for a way to build another power station. It was not possible to use the Reuss hydropower, as its water rights had already been granted to the SBB. The engineering office HE Gruner from Basel therefore worked out a project in which the water of the Leitschachbach, the Intschialpbach and some springs on the Arniberg plateau at an altitude of 1370 m is to be collected and processed in a center in the valley at an altitude of 520 m . In the dry winter months, a possible output of 1,400 hp was expected, in the water-rich summer 10,000 to 15,000 hp should be available. The concession was granted in 1907 and the construction costs were estimated at 3 million francs .

During the construction of the project, the purpose of the power plant was changed. The plant should not only supply energy to the Altdorf power station, but also cover the load peaks of the Rathausen power station . To this end, Elektrizitätswerk Rathausen AG , the forerunner of CKW, took a 62% stake in the Altdorf power station and financed the construction of the Arniberg power station. The changes to the project were made based on suggestions from AG Motor from Baden , a predecessor company of what later became Motor-Columbus . The machine house had to be enlarged for the new task so that additional turbines could be installed if required later. The system also had to be designed so that it could work with the different frequencies of the two networks - Altdorf was still working with a frequency of 48 Hz, while Rathausen was working with 42 Hz.

Wooden channel over the arniboden

The machine house started operations in August 1910, although the reservoir was not yet completed. For this purpose, the water from the supply line to the reservoir was led with a temporary wooden channel over the arniboil directly to the inlet in the pressure pipe. In the turbine building only as were initially converters usable machine group I with 1,500 horsepower and the engine group set up with 3000 hp II, 1912 was followed by the machine group III. The power plant worked in conjunction with the Rathausen power plant, the Bürglen power plant and, from 1925, also with the Gurtnellen power plant .

In 1918, the Arnibach was also captured and fed directly into the pressure line of the power plant with an 80 kW pumping station near Ober Axeli. In the beginning, this system was only in operation in winter. In 1944 the output of the turbines was increased, from 1967 to 1969 the system was renewed and new machine groups were installed. New turbine regulators were installed in the winters of 2011 and 2012. The annual production in 2012 was around 46 GWh, which corresponds to around a fifth of the electricity generated by the Altdorf power station.

technology

The machine house is supplied with water from the Arnisee with a net volume of 180,000 m³. The lake is supplied with water from the Leitschachbach and the Intschialpbach.

Pressure line

Pressure pipe at anchorage P12. The short piece of pipe is visible on the left, which has already been laid in the anchoring in preparation for a second pipe run.

The 2067 m long pressure line from the Arnisee to the machine house consisted of welded tubes with a diameter of 470 to 600 mm, whereby initially only one line was laid on the route intended for two lines. Only at the inlet in the eastern dam of the reservoir, in the valve chamber and at the anchoring blocks, short sections of the second pipeline have already been installed.

The first 430 m of the pressure pipeline run underground, the rest of the pipeline runs above ground except for an 82 m long tunnel at Axli. The pipes were supplied by the still existing company Ferrum from Katowice and were designed for a pressure of 85 bar in the lower part of the line. The raw material for the pipes was sheet metal made of Siemens-Martin steel , which was manufactured by the Upper Silesian Railway Requirement Actien in Friedenshütte, a district of today's Ruda Śląska .

The distribution pipe to the individual machine groups was arranged at the lower end of the pressure line. The branches to the four intended machine groups were designed as fittings. They were manufactured by Von Roll based on drawings by Bell Maschinenfabrik and each contained the shut-off device for the relevant machine group.

Machine house

The headquarters of the Reuss was built for four machine groups, there were, however, only set the two at the beginning: as converters usable machine group I with 1,500 hp and the machine group II with 3000 hp.

Machine group I consisted of a Pelton turbine with an output of 1,300 hp that drove two three-phase generators. The smaller 16-pole generator had an output of 500 kVA and supplied electricity with a frequency of 48 Hz to the Altdorf electricity company, the larger 14-pole generator with an output of 1000 kVA supplied 42 Hz electricity to the Rathausen electricity company. This group of machines could also be operated as a rotating converter , so that it could be used as a network coupling between the two power plants. The turbine came from Bell, the generators from the Alioth electricity company from Münchenstein near Basel .

Machine group II consisted of a Pelton turbine from Bell that drove a three-phase generator from BBC . The turbine had an output of 3000 HP, the generator one of 2600 kVA. The foundations for three further machine groups of this type were prepared in the machine house.

The transformers of the machine groups were arranged in the rear part of the machine house in the basement. The transmission line to Rathausen was operated with a voltage of 42.5 kV, the one to Altdorf with a voltage of 15 kV. The podium with the control room was arranged above the transformers. Removable covers were embedded in the floor, which enabled access to the transformers with the overhead crane in the machine hall.

The power of the machine house has been increased again and again over the years and around 1920 it was switched to operation with a mains frequency of 50 Hz.

Power plant Arniberg
year Machine group I Machine group II Machine group III total source
1910 1500 hp 3000 hp 4500 hp
1912 1500 hp 3000 hp 3000 hp 7500 hp
1944 1500 hp 3600 hp 4100 hp 9200 hp
1969 6.5 MW 6.5 MW 13 MW (17,700 hp)
Machine room at the Amsteg headquarters with the two 6.5 MW machine sets

At the end of the 1960s, the system was completely overhauled and the machine groups replaced. Two 6.5 MW groups with a horizontal axis were installed, each consisting of a single-jet Pelton turbine and a generator.

Leitschach small power station

Engine room of the small power station Leitschach World icon

In 2009 the small power plant in Leitschach was put into operation. It uses the water from the Leitschach socket to drive a through-flow turbine before it is fed to the Arni lake via the Torli collection shaft. The fall height is 23 m, the output is 180 kW, the annual production 550 MWh.

Situation map

Arniberg power plant

See also

literature

Web links

Commons : Kraftwerk Arniberg  - Collection of images, videos and audio files

Individual evidence

  1. a b Federal Office for Energy SFOE (Ed.): Statistics of the hydropower plants in Switzerland . January 1, 2020 ( admin.ch [accessed on May 2, 2020] attachment number 301000).
  2. In Switzerland, all power plants that cannot store at least a quarter of winter production are run-of-river power plants. Source: Statistics of hydropower plants
  3. a b c d EWA is subjecting pioneer power plant to a makeover . In: Zek Hydro . Volume 10, December 2012, p. 37-39 ( docplayer.org ).
  4. a b Arniwerk . In: Illustrated Swiss craft newspaper . tape 25 , no. 50 , 1909, pp. 781-782 ( e-periodica.ch ).
  5. a b Schweizerische Bauzeitung part 1
  6. ^ Electricity works Altdorf AG: history. Retrieved December 8, 2018 .
  7. a b Statistics hydropower plants in Switzerland . January 1, 1947, p. 66-67 .
  8. a b c Schweizerische Bauzeitung, part 2
  9. ^ Cours d'eau et energy . tape 13 . Swiss Water Management Association, 1921, ISSN  0043-096X , OCLC 2536193 , p. 159 (French, limited preview in Google Book search).
  10. Hannes Gysling: Comprehensive fitness program for EWA substation . In: Schneider Live . 2012, p. 30 .
  11. Werner Jauch: KW Leitschach on the sun terrace of Arni . In: The small power plant . No. 74 , 2010, pp. 48-52 ( pim.com [PDF]).