List of geothermal power plants in Germany
The list provides an overview of geothermal power plants in Germany.
zgW = supplied geothermal heat output approx.
TWT = thermal water
temperature
KW name | Gross power in MW |
Net power in MW |
zgW in MW |
TWT | principle | Location | operator | Remarks |
---|---|---|---|---|---|---|---|---|
Geothermal heating plant Waren (Müritz) | ? | ? | 3.6 | 60 ° C | Organic Rankine Cycle | Goods (Müritz) | Stadtwerke Waren GmbH | Germany's first geothermal power plant in the megawatt output range for heat supply. |
Neustadt-Glewe geothermal power plant | 0.230 | 0.075 | 3 | 98 ° C | Organic Rankine Cycle | Neustadt-Glewe | Erdwärme-Kraft GbR ( Vattenfall Europe Berlin , WEMAG AG (Schwerin), Energie Südwest (Landau in der Pfalz)) | lowest thermal water temperature worldwide; in operation from 2003 to 2010 |
Dürrnhaar geothermal power plant | approx. 5.5 MWel | ? | 50 | 135 ° C | Organic Rankine Cycle | Thin hair | Stadtwerke München GmbH | first project financing for a geothermal power plant in Germany. |
Geothermal power plant Kirchstockach | approx. 5.5 MWel | ? | 50 | 136 ° C | Organic Rankine Cycle | Kirchstockach | Stadtwerke München GmbH | Project finance |
Landau geothermal power plant | 6 - 8 | 3 | ? | 160 ° C | Organic Rankine Cycle | Landau in the Palatinate | geox (Energie Südwest, Pfalzwerke ) | in operation from 2007 to 2014 |
Kirchweidach geothermal power plant | ? | 2.3 el 40 th |
? | 130 ° C | Organic Rankine Cycle | Kirchweidach | Kirchweidacher Energie GmbH | |
Geothermal power plant Traunreut | ? | 3-4 el ? th |
? | 118 ° C | Organic Rankine Cycle | Traunreut | Geothermal power plant company Traunreut | Electricity delivery from 3rd quarter 2014. |
Geothermal power plant Holzkirchen | approx. 3.4 MWel | ? | ? | 155 ° C | Organic Rankine Cycle | Holzkirchen (Upper Bavaria) | Geothermal Holzkirchen GmbH | Trial operation of the power plant from the 1st quarter of 2019 |
Sauerlach geothermal power plant | approx. 5 MWel | ? | ? | 140 ° C | Organic Rankine Cycle | Sauerlach | Stadtwerke München GmbH | |
Geothermal power plant Laufzorn | 4.3 el | ? | 38 | 130 ° C | Organic Rankine Cycle | Oberhaching | Erdwärme Grünwald GmbH | |
Taufkirchen geothermal power plant | 4.3 el | ? | ? | 136 ° C | Kalina cycle | Taufkirchen | Daldrup & Söhne AG, from 2020 IKAV Group | |
Geothermal power plant Unterhaching | 3.36 el /
Max. 38 th |
? | 38 | 122 ° C | Kalina cycle | Unterhaching | Geothermal energy Unterhaching GmbH & Co KG (Unterhaching municipality) | Kalina power plant has not been in operation since 2017 |
Insheim geothermal power plant | 6 el. | 4.8 el. , Optional 6-10 th. | ? | 165 ° C | Organic Rankine Cycle | Insheim | Pfalzwerke geofuture GmbH | |
Geothermal heating plant Unterföhring | 22 th | ? | 87 ° C 93 ° C |
Unterföhring | GEOVOL, owned by the Unterföhring municipality | Appendix 1 since 2009 Appendix 2 since 2016 |
||
Kirchanschöring geothermal power plant | Kirchanschöring | Rupertiwinkel GmbH | Start of construction 04.2020 |
Individual evidence
- ↑ Project info - Landau geothermal power plant ( Memento of the original from September 22, 2013 in the Internet Archive ) Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice.
- ↑ The geothermal power plant in Traunreut. Retrieved September 1, 2015 .
- ↑ Daldrup & Söhne AG press release: Daldrup & Söhne AG: As part of the announced realignment, Daldrup & Söhne AG is selling the Geysir group with geothermal power plants to the IKAV group. In: www.dgap.de. January 15, 2020, accessed January 25, 2020 .
- ↑ geothermie-insheim.de , accessed on October 30, 2014