East Anglia offshore wind farm

from Wikipedia, the free encyclopedia
Offshore wind farm "East Anglia"
location
East Anglia offshore wind farm (North Sea)
East Anglia offshore wind farm
Coordinates 52 ° 54 '28 "  N , 2 ° 37' 43"  E Coordinates: 52 ° 54 '28 "  N , 2 ° 37' 43"  E
country United Kingdom
Waters North Sea
Data
Type Offshore wind farm
Primary energy Wind energy
power One: 714 MW
One North: 800 MW
Two: 900 MW
Three: 1200 MW
(up to 7,200 MW in total)
owner ScottishPower Renewables
turbine One: 102 × Siemens Gamesa SWT-7.0-154
Energy fed in per year > 2,300 GWh
Website scottishpowerrenewables.com
was standing November 2019
f2

East Anglia is the name of several planned offshore wind farms in the English Exclusive Economic Zone of the United Kingdom in the North Sea , the first of which is about to go into operation. Up to six different wind farms with a capacity of 7200  MW could be realized. The name East Anglia is related to the region of East Anglia .

Construction of the East Anglia One sub-project began in April 2018. Implementation should be completed by 2020. East Anglia One can supply nearly 600,000 households with electricity. The East Anglia Three sub-area was approved in August 2017.

East Anglia One

Following a tender by the British government, sub-area One was awarded £ 119.89 per megawatt hour for 714 megawatts in February 2015  . Via a contract for difference , the feed-in tariff for the electricity is guaranteed by the state to the operator for 15 years ( present value from 2012). The successful bidder was East Anglia One Limited , an operating company of ScottishPower Renewables . In June 2015, the project developer named Siemens Gamesa as the preferred supplier. A total of 102 Siemens Gamesa SWT-7.0-154 turbines, each with 7 MW, have an installed capacity of 714 MW. The total investment was put at £ 2½ billion.

History and construction

In February 2016, ScottishPower Renewables announced that it had made its final decision to invest in East Anglia One. The 102 foundations were installed from April 2018 to July 2019. The Van Oord company took on all transport and installation work. The foundations are of the jacket type (65 meters high), which were manufactured by the companies Lamprell and a joint venture between Navantia and Windar and were delivered via the Dutch port city of Vlissingen . The first turbine was installed on June 12, 2019. The turbines and rotor blades are pre-assembled in Great Yarmouth and loaded for sea transport.

The 167 meter high transformer platform ("Andalusia II") built at Navantia in Puerto Real (Spain ) was installed in August 2018 . Here, the electricity produced by the 102  wind turbines is converted from 66 kV to 220 kV and transported over two 85-kilometer submarine cables to the land, where it is to be fed into the British power grid in Bramford ( Suffolk ). The wind farm will be monitored and controlled from the maintenance center in the port in Lowestoft .

East Anglia One North

The East Anglia One North sub-area is at the planning stage. According to information from ScottishPower Renewables, plants for 800 MW would be realized there over an area of ​​209 km².

East Anglia Two

About 37 kilometers off the coast of the city of Lowestoft is the East Anglia Two sub-area , in which 900 MW could be installed over an area of ​​257 km². It is in the planning stage.

East Anglia Three

East Anglia Three is another sub-area that was approved in August 2017. According to the British government, it will have a capacity of 1,200 MW. The tendering process ran until December 2016. On an area of ​​305 km², 172 systems can supply almost 900,000 households. The realization is carried out by the company ScottishPower Renewables .

See also

Web links

Iberdrola : United by the wind on YouTube , November 19, 2019, accessed December 13, 2019 (documentary via East Anglia ONE).

Individual evidence

  1. a b c Approval granted for 1,200 MW offshore wind farm. iwr.de, August 9, 2017, accessed on August 10, 2017 .
  2. ^ A b Final Investment Decision in Place for East Anglia One. offshorewind.biz, February 24, 2016, accessed on September 3, 2016 .
  3. Siemens in lead for 714MW UK deal. windpoweroffshore.com, June 5, 2015, accessed on September 3, 2016 .
  4. ^ East Anglia ONE. scottishpowerrenewables.com, accessed September 3, 2016 .
  5. Van Oord installs final East Anglia One jacket . www.offshorewind.biz , July 18, 2019, accessed September 6, 2019
  6. Bokalift 1 Starts Installing East Anglia ONE Pin Piles. In: offshorewind.biz. April 16, 2018, accessed April 18, 2018 .
  7. Iberdrola is building the mega wind farm . In: Hansa , issue 7/2019, pp. 66/67
  8. ^ East Anglia ONE North. scottishpowerrenewables.com, accessed September 3, 2016 .
  9. ^ East Anglia TWO. scottishpowerrenewables.com, accessed September 3, 2016 .
  10. ^ East Anglia THREE Offshore Wind Farm. infrastructure.planninginspectorate.gov.uk, accessed September 3, 2016 .
  11. ^ East Anglia Three. scottishpowerrenewables.com, accessed September 3, 2016 .