Chavalon power station

from Wikipedia, the free encyclopedia
Chavalon thermal power station
ETH-BIB LBS L1-674285 Usine de Chavalon 060667.jpg
location
Chavalon power plant (canton of Valais)
Chavalon power station
Coordinates 556 888  /  132994 coordinates: 46 ° 20 '49 "  N , 6 ° 52' 43"  O ; CH1903:  five hundred and fifty-six thousand eight hundred and eighty-eight  /  132994
country Switzerland
Data
Type Steam power plant
Primary energy Fossil energy
fuel Heavy fuel oil
power 2 × 142 MW
Start of operations 1965
Shutdown 1999
Chimney height 120 m
Website http://www.chavalon.ch/de-CH/
f2

The Chavalon thermal power plant (in French, Centrale Thermique de Vouvry ) was one of the few conventional thermal power plants in Switzerland .

Heavy oil power plant (1965–1999)

The decommissioned power plant is located on a hill.

The power plant, which is heated with heavy oil, is located on the southern slope of the Rhone Valley on a terrace at 825  m above sea level. M. , 450 m above the valley floor, in the municipality of Vouvry , Canton of Valais . The Chavalon thermal power station went into operation on September 22, 1965 and was shut down in September 1999. Heavy oil was burned, which was produced in the neighboring Collombey refinery as a residue from fuel production. It had an electrical output of 2 × 142  MW .

All buildings are still there. The unusual location on the slope was chosen so that the smoke gases can escape better. With a height of 120 meters, the power plant's chimney is one of the highest chimneys in Switzerland.

Planning for a gas power plant

In the following years, plans began to build a 400 MW gas power plant on the site of the decommissioned oil power plant . The new CO 2 compensation law, however, stipulates that new gas-fired power plants can only be approved if they use waste heat ( combined heat and power ). When planning the gas power plant, an exhaust gas temperature of 25 ° C was envisaged and this is too little for waste heat recovery. For this purpose, other gas-fired power plants are planned in Switzerland where the use of waste heat - for example for nearby paper mills or the Cressier refinery - was planned from the start. Because Chavalon is away from the industrial zones, economic competitiveness is a problem.

In January 2007, a building application was submitted to the responsible municipality for the new power plant. According to the building permit, the old plant should have been dismantled in 2007 and the new power plant should have been built in 2008 and 2009. Approval by the municipality of Vouvry took place in September 2009. However, there have been objections, including from environmental organizations, some of which were granted by the canton of Valais. The system is currently (August 2011) in an unchanged condition. A compensation agreement was negotiated with the Federal Office for the Environment at the end of September 2012. The approval process can thus be continued. In the summer of 2017, the project was abandoned for economic reasons and as a reaction to the Energy Strategy 2050 .

Technical specifications

The plans for the new power plant provide for the following key data:

  • Output: 400 MW
  • Planned operating time / year: 5,500 hours
  • Annual production: 2.2 TWh
  • Estimated investment: CHF 380 million
  • Service life: 25 years

See also

Web links

Commons : Chavalon Thermal Power Plant  - Collection of images, videos and audio files

Individual evidence

  1. chavalon.ch: project. ( Memento of the original from September 9, 2011 in the Internet Archive ) Info: The archive link was automatically inserted and not yet checked. Please check the original and archive link according to the instructions and then remove this notice. Retrieved August 2, 2011 @1@ 2Template: Webachiv / IABot / www.chavalon.ch
  2. ^ M. Beniston: From turbulence to climate. Verlag Springer, 1998, ISBN 3-540-63495-9 , p. 202 ( limited preview in Google book search).
  3. P. Jeanneret: Popistes: histoire du Parti ouvrier et populaire vaudois, 1943-2001. Editions d'en bas, 2002, ISBN 2-829-00272-5 , p. 519 ( limited preview in Google book search).
  4. NZZ, January 24, 2007 planning application applied for
  5. 24heures July 5, 2010 , accessed October 31, 2010 (in French)
  6. ↑ Clear the way for the Chavalon gas-fired power station Article in the Tages-Anzeiger on September 26, 2012
  7. The end is not a shame, but alarming. NZZ, June 30, 2017, accessed on April 29, 2019 .
  8. Energy suppliers abandon plans for Chavalon VS gas-fired combined-cycle power plant. Blick, June 30, 2017, accessed April 29, 2019 .