Erstfeldertal power plant

from Wikipedia, the free encyclopedia
Erstfeldertal power plant
location
Erstfeldertal power plant (canton Uri)
Erstfeldertal power plant
Coordinates 691784  /  185955
country SwitzerlandSwitzerland Switzerland
Canton of UriCanton of Uri Uri
place Erstfeld
Waters Alpbach
Height upstream 730  m above sea level M.
power plant
owner Erstfeld municipal
utilities : 38% Altdorf electricity station: 38%
Canton Uri : 16%
Uri corporation: 8%
operator Kraftwerk Erstfeldertal AG
Start of planning 2017
construction time May 2019 – December 2020
Start of operation 2020
technology
Bottleneck performance 11.5 megawatts
Average
height of fall
232 m
Expansion flow 5.5 m³ / s
Standard work capacity 32 million kWh / year
Turbines 3 × Pelton turbine :

Machine 1 + 2: each 5.75 MW Machine 3: 0.65 MW

Others
Website kw-erstfeldertal.ch
was standing June 2020

The power plant Erstfeldertal is a medium pressure - hydropower plant at Alpbach in the town of Erstfeld in the canton of Uri in Switzerland , which is to go in December 2020 operation.

history

Attempts were made as early as 1918 to dam the Fulensee at an altitude of 1705 m at the back of the Erstfeldertal, but this was not pursued any further. A water intake on the Alpbach was also part of the Urseren power plant project of 1943/44 , where the water would have been processed as a secondary inflow in the headquarters in Erstfeld. The project to use the power of the Alpbach was not pursued for a long time because the community of Erstfeld feared that drinking water sources would dry up. In 2017 the Altdorf electricity company resumed a project with a reduced height of fall, but there was a need to hurry to prevent the cost-covering feed-in remuneration (KEV) guaranteed by the Erstfeld municipal utility from being forfeited. The license application for the power plant was submitted in March 2018, and the building permit for the power plant was granted in November of the same year. The groundbreaking ceremony for the construction of the power plant took place in May 2019 , and commissioning is scheduled for December 2020.

technology

The water of the Alpbach is collected at Schopfen , where it is treated in an underground desander before it is carried in a 1,100 m long penstock to the headquarters in the Spätach district of Erstfeld. Three Pelton turbines will be installed in the machine house - two have an output of 5.75 MW each, a third an output of 0.65 MW.

literature

  • Erstfeldertal power plant - from vision to tangible reality . In: ZEK Hydro . February 2019, p. 49–51 ( kw-erstfeldertal.ch [PDF]).

Individual evidence

  1. E. Meyer-Peter, Th. Frey: The 1943/44 project of the Urseren power plants: structural report, prepared on behalf of the study syndicate for the Urseren power plants, part 3: Description of the plants: power plants . In: Schweizerische Bauzeitung . tape 126 , no. 13 , September 29, 1945, p. 144 , doi : 10.5169 / seals-83730 .
  2. ZEK Hydro, Infobox, p. 50