Stalvedro power plant

from Wikipedia, the free encyclopedia
Stalvedro power plant
Machine house of the Stalvedro power plant to the right of the machine house of the Ritom power plant.  Picture from 1980
Machine house of the Stalvedro power plant to the right of the machine house of the Ritom power plant . Picture from 1980
location
Stalvedro power plant (Canton Ticino)
Stalvedro power plant
Coordinates 695085  /  152546
country SwitzerlandSwitzerland Switzerland
Canton of TicinoCanton of Ticino Ticino
place Piotta
Waters Ticino
Height upstream 1135  m above sea level M.
power plant
owner AET
operator AET
Start of planning 1964
construction time 1966-1968
Start of operation 1968
technology
Bottleneck performance 13 megawatts
Average
height of fall
132.5 m
Expansion flow 12 m³ / s
Standard work capacity 61 million kWh / year
Turbines 2 Francis turbines
Others
was standing 2020

The power plant Stalvedro , Italian Impianto idroelettrico Stalvedro , is a medium pressure - hydropower plant , which in 1966 to 1968 by the Azienda Elettrica Ticinese was built (AET) and the slope of the river Ticino in the Stalvedro Gorge between Airolo and Piotta exploits.

technology

The water is the 370 000 m³ comprehensive balancing reservoir Airolo the power plant Lucendro at an average height of 1,130  m above sea level. M. and passed into a 5.6 km long inlet tunnel on the orographic left side of the valley. This also absorbs the water from the Val Canaria , which is near Airolo between the settlements of Valle and Madrano at an altitude of 1144  m above sea level. M. taken is. An underground armored pressure shaft at an angle of 45 ° leads from the valve chamber at the end of the inlet tunnel to the machine house . This is located at Piotta at an altitude of 1002  m above sea level. M. (floor of the machine room) directly next to the machine house of the Ritom power plant commissioned by SBB in 1920 . The water used is returned to the Ticino River.

With the expansion of the Ritom power plant, an equalization basin ▼ with a capacity of 100,000 m³ will be created between the two machine houses and Autobahn 2 , which on the one hand ensures an even outflow of the underwater of the two power plants into the river, and on the other allows the underwater of the Stalvedro power plant to flow with it to pump the Ritom II power plant into Lake Ritom , which enables a more flexible use of the water for electricity production in the Leventina.

Two horizontal-axis Francis turbines are installed in the machine house of the Stalvedro power station , each driving a generator with an output of 6.5 MW . Every year 61 million kWh of renewable energy are generated, which is sufficient to supply 15,000 average households.

See also

literature

  • AET (ed.): Impianto idroelettrico Stalvedro . (Italian, aet.ch ).