Pre-lock Deesbach

from Wikipedia, the free encyclopedia
Pre- dam Deesbach
(Leibis-Lichte dam)
Deesbach-Vorsperre.jpg
Location: District of Saalfeld-Rudolstadt
Tributaries: Light
Drain: Light
Larger places nearby: Deesbach , Oberweißbach
Pre-barrier Deesbach (Thuringia)
Pre-lock Deesbach
Coordinates 50 ° 34 '21 "  N , 11 ° 10' 8"  E Coordinates: 50 ° 34 '21 "  N , 11 ° 10' 8"  E
Data on the structure
Construction time: 1981-1991
Height above valley floor: 42.5 m
Height above foundation level : 45 m
Height of the structure crown: 463.50 m
Building volume: 300,000 m³
Crown length: 178 m
Crown width: 6 m
Base width: 180.6 m
Slope slope on the air side : 1: 1.75 and 1: 1.70
Slope slope on the water side : 1: 2
Data on the reservoir
Altitude (at congestion destination ) 461  m
Water surface 22.0 hadep1
Reservoir length 1.2 km
Storage space 3.2 million m³
Catchment area 49.5 km²
Design flood : 35 or 40.5 m³ / s
Particularities:

Bottom outlet housed in the construction-time diversion tunnel

The deesbach forebay is the Leibis-light in front. It is located in the Lichtetal, near the villages of Deesbach , Lichte , Meura and Unterweißbach in the Saalfeld-Rudolstadt district , Thuringia . It was put into operation in 1991 and dams the lights .

Use / function

The construction of the Leibis-Lichte dam did not begin until long after the pre- dam was completed. However, this was planned from the beginning as a pre-lock and not for the direct drinking water supply. It temporarily took over the function of a dam , because from 1992 to 2005 over 100,000 inhabitants in the Saalfeld-Rudolstadt district and in the Saale-Orla district had to be supplied with drinking water from it. In 2005 the permit for the temporary extraction of raw water expired. After the Leibis-Lichte dam went into operation in 2008, the Deesbach dam finally took over its actual function as a preliminary dam (pre-cleaning, sedimentation). It is now backed up on the air side by the main barrier.

Dam / structures

The dam is a rubble dam made of Posidonia slate with asphalt concrete - outer skin seal made of two sealing layers, a base layer and a drainage layer. The flood relief consists of a crown overflow on the right slope with a collecting and weft channel that leads into a stilling basin . The raw water was taken through 2 inlets, one of which has a swiveling pipe with which 18,000 m³ per day could be taken. The water was led to the Zeigerheim drinking water treatment plant near Bad Blankenburg via a 3.5 km long DN 500 steel pipeline, which was laid at the bottom of the current reservoir of the main dam, and via the eleven kilometers of "Lichtstollen" I and II the raw water of the Leibis / Lichte dam is cleaned.

Others

The pre-lock is also often used for fishing . However, it can only be reached on foot or by bike, along the main dam from Unterweißbach or along the tributaries from Deesbach. A path is also signposted from the Froebel Tower .

See also

Web links

literature

  • Dams in Thuringia . Thuringian dam administration, author college, 1993.
  • Dams and remote water supply systems in Thuringia . Harald Roscher, Thuringian long-distance water supply, 2006.