Ferlach-Maria Rain run-of-river power plant

from Wikipedia, the free encyclopedia
Ferlach-Maria Rain run-of-river power plant
Ferlach-Maria Rain run-of-river power plant.jpg
location
Ferlach-Maria Rain run-of-river power plant (Carinthia)
Ferlach-Maria Rain run-of-river power plant
Coordinates 46 ° 32 '47 "  N , 14 ° 17' 55"  E Coordinates: 46 ° 32 '47 "  N , 14 ° 17' 55"  E
country Austria
Waters Outside
Data
power 75 MW
owner VERBUND Hydro Power AG
operator VERBUND Hydro Power AG
Project start 1971
Start of operations 1975
turbine Two Kaplan turbines
Energy fed in per year 318 GWh
f2

The Ferlach-Maria Rain run-of-river power plant is a run-of- river power plant on the Drau between the communities of Ferlach and Maria Rain . The power plant dams the Drau over ten kilometers to the Feistritz / Ludmannsdorf power plant above, thus forming the Ferlach reservoir .

Technical specifications

The power plant was built between 1971 and 1975 by the ÖDK in cooperation with Kelag . It is unmanned and controlled from the Feistritz / Ludmannsdorf power station. The nominal output is 75  MW . The annual production is 318  GWh . The water level is approx. 17 m; To increase the head, the river bed below the power plant was lowered by 4.5 m. The two Kaplan turbines each produce a maximum of 39 MW, the associated three-phase synchronous generators a maximum of 50 MVA.

See also

Web links