Vuhred power station
Vuhred power station | ||
---|---|---|
location | ||
|
||
Coordinates | 46 ° 35 ′ 15 ″ N , 15 ° 16 ′ 30 ″ E | |
country | Slovenia | |
place | Radlje ob Dravi | |
Waters | Outside | |
power plant | ||
owner | DEM | |
operator | DEM | |
construction time | 1952 to 1958 | |
Start of operation | 1956 | |
technology | ||
Bottleneck performance | 72.3 megawatts | |
Average height of fall |
17.41 m | |
Expansion flow | 550 m³ / s | |
Standard work capacity | 297 million kWh / year | |
Turbines | Kaplan turbines : 3 × 24.1 MW | |
Others |
The Vuhred power plant ( Hidroelectrarna Vuhred in Slovenian ) is a run-of-river power plant on the Drava in the municipality of Radlje ob Dravi , Slovenia . It has an installed capacity of 72.3 MW .
The power plant is owned by Dravske elektrarne Maribor (DEM) and is also operated by DEM.
Barrier structure
The barrier structure is a weir system with four weir fields; Between the weir fields there is a machine house with a turbine. Each weir field is 17 m wide. A maximum of 5800 m³ / s can be discharged via the weir system.
Reservoir
When the reservoir is fully blocked, it extends over a length of 13.1 km and holds 10.3 million m³ of water, of which 2.2 million can be used for electricity generation.
power plant
The power plant was built from 1952 to 1958. It went into operation in 1956 with two machines; the third machine followed in 1958. The power plant has an installed capacity of 72.3 MW . The average annual production is 297 million kWh . The three Kaplan turbines each have a maximum output of 24.1 MW, the associated generators 30 MVA . The fall height is 17.41 m. The flow rate is 550 m³ / s.
See also
Web links
Individual evidence
- ↑ a b c d Vuhred power plant: the result of domestic knowledge. Dravske elektrarne Maribor , accessed on December 15, 2019 .
- ↑ a b Vuhred Hydroelectric Poqwer Plant Slovenia. Global Energy Observatory, accessed December 15, 2019 .