Blayais Nuclear Power Plant
Blayais Nuclear Power Plant | ||
---|---|---|
Blayais Nuclear Power Plant | ||
location | ||
|
||
Coordinates | 45 ° 15 '22 " N , 0 ° 41' 30" W | |
Country: | France | |
Data | ||
Owner: | EDF | |
Operator: | EDF | |
Project start: | 1976 | |
Commercial operation: | June 12, 1981 | |
Active reactors (gross): |
4 (3,804 MW) | |
Energy fed in in 2016: | 24,276 GWh | |
Energy fed in since commissioning: | 814,140 GWh | |
Website: | Side of the operator | |
Was standing: | August 25, 2017 | |
The data source of the respective entries can be found in the documentation . |
The nuclear power plant Blayais is the French community Blaye in the region Nouvelle-Aquitaine in the Gironde department . The nuclear power plant, which consists of four pressurized water reactors , is located on the right bank of the Gironde estuary , about 60 kilometers from Bordeaux and 80 kilometers from Royan .
Key data
The 227 hectare nuclear power plant area is located in a 6000 hectare marshland and employs around 1300 people. The operator of the nuclear power plant is the French company Électricité de France (EDF). The four pressurized water reactors have a net capacity of each 910 megawatts (MW) and a gross capacity of 951 MW. The total installed capacity is 3804 MW, making the nuclear power plant one of the larger in France. It feeds an average of 24 billion kilowatt hours into the public power grid every year .
To cool the system, water is taken from the Gironde over a length of 400 meters by means of underwater pipes, which is fed back into the river after the cooling process in the reactors in the center of the estuary, 2.2 kilometers from the bank. This distance is necessary, on the one hand, so that the heated water is not sucked in again, and, on the other hand, so that the water is cool enough and far enough away from the bank to return to the river to protect the habitat of the fish, which are mainly in the bank not to disturb too much.
Construction of the first two reactor blocks began on January 1, 1977. Unit 1 went into operation on June 12, 1981 and Unit 2 on July 17, 1982. On April 1, 1978, the construction of two further reactor blocks began, which were put into operation on May 16, 1983 and August 17, 1983.
safety
Flood
Hurricane Martin caused severe flooding in the area of the nuclear power plant on the evening of December 27, 1999, which led to a category 2 accident on the International Rating Scale for Nuclear Events (INES 2). At this point the third reactor block was shut down for routine maintenance. The storm initially caused disruptions in the 400 kV network, which led to the automatic shutdown of reactor units 2 and 4. The storm then pushed the Gironde water over the protective dikes into the site of the nuclear power plant. The water flooded underground areas of the reactor buildings of units 1 and 2. Parts of the cooling system and emergency cooling as well as other safety devices were also flooded.
According to the EDF, the cooling of the reactor blocks concerned was always guaranteed. The operating organization CGT also announced in a statement that two out of three cooling circuits had remained functional, which was sufficient to cool the system. The fact that, as a result of the flooding, the functioning of the safety devices could no longer be relied on in an emergency is more serious. The flood incident later led to investigations at other - including German - nuclear power plants about the effects of a possible flood.
The cost of this incident is estimated at $ 63 million.
earthquake
In the event of a strong earthquake, the emergency cooling could fail. According to a report by the atomic safety authority ASN in October 2002, certain protective functions in the event of earthquakes that ensure that the reactor units cool down could no longer be guaranteed.
Data of the reactor blocks
The Blayais nuclear power plant has a total of four blocks :
Reactor block | Reactor type | net power |
gross power |
start of building | Network synchronization |
Commercialization of essential operation |
switching off processing |
---|---|---|---|---|---|---|---|
Blayais 1 | Pressurized water reactor | 910 MW | 951 MW | 01/01/1977 | 06/12/1981 | December 01, 1981 | (Planned for 2021) |
Blayais 2 | Pressurized water reactor | 910 MW | 951 MW | 01/01/1977 | 07/17/1982 | 02/01/1983 | (Planned for 2023) |
Blayais 3 | Pressurized water reactor | 910 MW | 951 MW | 04/01/1978 | 08/17/1983 | 11/14/1983 | (Planned for 2023) |
Blayais 4 | Pressurized water reactor | 910 MW | 951 MW | 04/01/1978 | 05/16/1983 | 10/01/1983 | (Planned for 2023) |
See also
Web links
- The nuclear power plant on the side of the operator (French)
- Nuclear power plants at risk. France fears a Fukushima scenario . Tagesschau , October 13, 2017, about Blayais, the dangerous situation in 1999
Individual evidence
- ↑ a b c Power Reactor Information System of the IAEA : "France (French Republic): Nuclear Power Reactors" (English)
- ↑ Centrale nucléaire du Blayais: "Le choc de 1999" . In: SudOuest.fr . ( sudouest.fr [accessed April 8, 2018]).
- ↑ tagesschau.de: Ruined nuclear power plants swallowed billions worldwide. Retrieved on March 13, 2018 (German).
- ↑ Energy Chronicle - French nuclear power plants not earthquake-proof