Elzer Berg tunnel

from Wikipedia, the free encyclopedia
Elzer Berg tunnel
Elzer Berg tunnel
Driver's cab perspective of a train approaching the south-east portal
traffic connection High-speed route Cologne – Rhine / Main
place Elz
length 1110 m
Number of tubes 1
construction
Client Deutsche Bahn
business
operator DB network
release 2002 (commercial commissioning)
location
Elzer Berg Tunnel (Hesse)
Red pog.svg
Red pog.svg
Coordinates
Northwest portal 50 ° 24 ′ 47 "  N , 7 ° 58 ′ 12"  E
Southeast portal 50 ° 24'35 "  N , 7 ° 59'6"  E

The Elzer Berg Tunnel is a 1110 m long railway tunnel on the high-speed line Cologne – Rhine / Main . It is located on Elzer Berg , in the area of ​​the Central Hessian municipality of Elz, and therefore bears his name.

The tube accommodates two tracks on a slab track , which can be driven on as planned at 300 km / h.

course

In the direction of Frankfurt, the north portal is located near the border between Rhineland-Palatinate and Hesse , on Hessian territory.

In a southerly direction the route runs in a right curve. The tube crosses under the federal motorway 3 in a south-westerly direction over a length of around 400 m. When going under part of the Elzer Forest , the biotope of the same name is also undercut. A water protection area with the Gückingen drinking water extraction system is also crossed under .

The gradient slopes down to the south portal with a gradient of up to 40 per mille.

After each section of the open road, the Lange Issel tunnel follows to the west and the Limburg tunnel to the south-east .

In the northern section of the tunnel, an emergency exit leads from the driving tunnel to the surface.

history

planning

At the end of 1994, the structure was planned to be 1,100 m long, with a maximum overburden of 30 m. According to these plans, the structure was to be built entirely using the mining method.

At the end of 1995, the planned length of the structure was 1110 m. At this point in time, the regional planning procedure in this section had been completed.

construction

The tunnel was built with a mining method over a length of 840 m; Due to the unfavorable soil conditions, an elm tunnel was sometimes used. An open construction method was used over a length of 270 m. Due to the presence of groundwater - the tunnel route passes the Kelterbaum spring at a distance of around 100 m - the tunnel was made pressure-tight.

business

A rescue exercise with 120 “passengers” and 450 rescue workers took place in the tunnel in November 2013.

Individual evidence

  1. a b c d DBProjekt GmbH Cologne – Rhein / Main, project management (publisher): New Cologne – Rhein / Main line: construction section middle, Lot B: Selters – Brechen , brochure (20 pages), Frankfurt am Main, January 1999, p. 4, 7.
  2. ^ Deutsche Bahn AG, Network Division, NBS Cologne – Rhein / Main (Ed.): New Cologne – Rhein / Main line. Hessen area. Plan approval sections Elz – Limburg (PFA 31.1–3) . Four-page brochure dated December 1994.
  3. ^ Deutsche Bahn AG, network division, project management for the Cologne – Rhein / Main line (publisher): route map for the new Cologne-Rhein / Main line . Map from November 1995, Frankfurt 1995.
  4. Franz-Josef Sehr : Emergency braking after a power failure brings the train to a stop in the 1,110-meter-long Elzer Berg tunnel. Landkreis-Limburg-Weilburg, November 9, 2013, accessed on June 11, 2019 .