380 kV line Bürstadt – Urberach

from Wikipedia, the free encyclopedia
Bürstadt – Urberach overhead line near Groß-Rohrheim

The 380 kV Bürstadt – Urberach line is a high-voltage three-phase overhead line in the south of the German state of Hesse . It connects the Bürstadt substation with the Urberach substation in the Rhine-Main area . The power generated in the Biblis nuclear power plant near the pipeline route was also fed into the pipeline via several branches. A further 380 kV line branches off to the west of Griesheim to Bischofsheim and, together with the continuing route to Urberach, forms a 380 kV ring around the Frankfurt metropolitan area.

The section from Graefenhausen to Urberach is particularly striking as it leads through a forest area and has numerous high masts. Due to the classification as an aviation obstacle, these are provided with a red and white warning paint. Due to the height and the conspicuous marking, these masts are a landmark in the southern Rhine-Main area that can be seen from afar and can be easily recognized from several kilometers away.

history

The exact time at which the line connection (RWE-internal designation Bl. 4591 ) was put into operation is not clearly documented. In any case, it was commissioned in the late 1970s or early 1980s. The Biblis nuclear power plant began generating electricity as early as 1975, and the Bürstadt substation also existed before that. The first expansion of the RWE transmission network in the Rhine-Main area to 380 kV (instead of 220 kV previously) dates back to 1979 and 1980, when the Koblenz – Marxheim section of the north-south line was replaced by a 380 kV line has been. From this line there is a continuation to the Bischofsheim substation, which in turn is connected to a branch line on the Bürstadt – Urberach line, which branches off west of Griesheim .

The commissioning enabled the southern and western Rhine-Main area to be connected to the 380 kV network and supplied with energy from the Biblis nuclear power plant. At the same time, a double-circuit 380 kV line from Urberach to Großkrotzenburg established the connection to the 380 kV network of PreussenElektra (now owned by TenneT TSO ).

course

380 kV line Bürstadt – Urberach (Hesse)
UW Bürstadt
UW Bürstadt
UW Urberach
UW Urberach
Route

The line begins in the Bürstadt substation, which is connected to the 380 kV Rommerskirchen – Hoheneck line, among other things . From there it runs north to the Biblis nuclear power plant, which was shut down in 2011 and is connected to the line via a few branches. After Biblis, the route turns first to the east, then to the northeast and crosses the A67 . It then meets the Flörsheim – Stuttgart traction power line and the north-south line and follows these parallel along Bergstrasse to the north to Pfungstadt. There, some electrical circuits branch off to the substation located directly on the line route. The line turns to the northwest and crosses the A 67 a second time. At Griesheim, the 380 kV line branches off to the Bischofsheim substation and the course changes to the northeast. Together with the traction power line, which leads to the Weiterstadt substation , the A 67 will be crossed a third time. The course leads northwards, then north-eastwards again and north of Graefenhausen finally eastwards.

After the former route of the north-south line has been crossed, the section leading through dense forest to Urberach begins. After crossing the A5 north of the Gräfenhausen service area, the route leads to the southeast, then again to the east and shortly before Messel to the northeast. Shortly before Urberach the direction changes from northeast to northwest and the Urberach substation is reached. The circuits are routed to the respective switchgear via several masts.

business

Masts

The line is laid on barrel masts for four 380 kV circuits. On the Biblis – Pfungstadt, Pfungstadt – Griesheim and Graefenhausen – Urberach sections, the masts carry an additional crossbeam below the 380 kV circuit. From Biblis to Pfungstadt this has not yet been roped, it was installed to have free capacity in the event of a possible expansion of the Biblis nuclear power plant. Between Pfungstadt and Griesheim there is a 220 kV circuit on the additional traverse, which changes to the 380 kV level at the junction masts near Griesheim from there to Urberach is also dimensioned for this voltage. The additional traverse from Graefenhausen originally served as a branch of the north-south line to Urberach, but has been free of stress since the line was dismantled in 2008. Between Egelsbach and Urberach these circuits are in operation with 110 kV and establish the connection between Urberach and Darmstadt.

The route through dense forest and the number of circuits, some of which are operated at the highest voltage level in the German power grid, required exceptionally high masts in the Graefenhausen-Urberach section. A total of 22 of these structures have a total height of over 100 meters. Due to this fact and the additional circumstances that there are two airfields ( Frankfurt Airport , Frankfurt-Egelsbach Airfield ) in the immediate vicinity of the pipeline route, 17 of the masts are equipped with various air traffic control systems.

These masts are painted red and white as an aviation obstacle, partly over the entire mast height. As prescribed for masts with a total height of over 100 m, there are red warning lights on the tips as lighting . Red warning markings, so-called flight warning balls, are installed on the earth wire between the masts to identify the routing of the cables .

Circuits

The four 380 kV circuits Biblis 1a , Biblis 2b , Ried West and Ried Ost run between Bürstadt and Biblis on the masts that are fully equipped here. The first two lead to the Biblis nuclear power plant, which has now been shut down, and from there comes the 220 kV Biblis 3c circuit , which is insulated for 380 kV, and swings onto the route. Together with Ried Ost , it branches off to the Pfungstadt substation, from where the 220 kV district Kranichstein Ost and the 380 kV district Griesheim Ost come , and two currently unused 380 kV circles begin there. One of them branches off with Ried West near Griesheim on the route to Bischofsheim, the 380 kV Erzhausen Nord district comes from there and continues towards Urberach. Two voltage-free 220 kV circuits begin near Graefenhausen and carry the 110 kV districts of Wixhausen and Offenthal North south of Egelsbach .

Conversions

New junction mast as part of the conversion of the Pfungstadt substation to 380 kV

The expansion of the Urberach – Weinheim line to 380 kV has been listed as project no. 19 in the Federal Requirements Plan Act since 2013. This is necessary in order to expand the capacities required in the course of the energy transition between producers in northern Germany and consumers in southern Germany. From Weinheim, a continuation of the line to Daxlanden near Karlsruhe is to be built by TransnetBW .

Between Urberach and Griesheim only the 220 kV and the currently unused circuit has to be converted to 380 kV, for which the line has to be re-wired. A second pipeline route must be built parallel to the existing route from Griesheim to Pfungstadt. The continuation to Weinheim receives completely new masts on the route of the existing 220 kV line.

To this end, the Pfungstadt substation will be converted from 220 kV to 380 kV, for which new 380 kV transformers will be put into operation step by step. Currently (9/2016) the first 380 kV power transformer is in operation and connected to the circuit leading to Urberach ( Griesheim Ost ). Two new masts had to be built for this. A second transformer will be put into operation in the near future. Only when the continuation of the line to Weinheim is to go into operation in 2022 will the last 220 kV transformers currently used by the north-south line from Pfungstadt disappear.

The Urberach substation is also currently being rebuilt. In March 2017, the masts of the previous 220 kV launch were dismantled, and the remaining 220 kV circuit has since been routed to the 220 kV switchgear via a provisionally laid underground cable within the system. The conversion to 380 kV between Pfungstadt and Urberach should be completed in 2018.

Web links

Commons : 380 kV Bürstadt – Urberach line  - collection of images, videos and audio files
  • amprion.net - Official website of the transmission system operator

Overhead lines in the extended Dreieich area . Retrieved August 17, 2015.

Individual evidence

  1. ^ From the history of electricity : VDI Information, accessed on May 31, 2016
  2. a b Amprion: Project description Urberach-Weinheim. Retrieved September 12, 2016 .
  3. TransntBW: Urberach-Pfungstadt-Weinheim-point G380 Altlussheim-Daxlanden. (No longer available online.) Archived from the original on December 22, 2015 ; Retrieved December 20, 2015 .
  4. Echo from January 29, 2014: The conversion of the substation will begin in February. (No longer available online.) Archived from the original on December 22, 2015 ; Retrieved December 20, 2015 . Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. @1@ 2Template: Webachiv / IABot / www.echo-online.de
  5. op-online.de of March 17, 2017: Power poles are now just scrap metal. Retrieved February 28, 2018 .