List of offshore wind farms in the UK

from Wikipedia, the free encyclopedia

The list of offshore wind farms in the UK contains the offshore wind farms in the Exclusive Economic Zone of the United Kingdom and offshore wind farms in the immediate coast.

The list is arranged by body of water. Within the individual categories, the wind farms are initially divided into operated, under construction and planned wind farms. The wind farms are then sorted alphabetically according to their (planned) completion date and then. Systems marked with a * are located in the immediate vicinity of the coast and are therefore also called near-shore systems.

Surname Power
(MW)
Wind turbine type
(power, rotor diameter)
Number of
WKAs
Coordinates status Commissioning (
year)
Sources, notes
English Channel
Rampion 400 Vestas V112-3.45
(3.45 MW, 112.0 m)
116 50 ° 40 ′ 12 "N, 0 ° 16 ′ 37" W. in operation 2018
Irish Sea
North Hoyle 60 Vestas V80-2.0
(2.0 MW, 80.0 m)
30th 53 ° 23 ′ 27 ″ N, 3 ° 27 ′ 9 ″ W. in operation 2003
Barrow 90 Vestas V90-3.0
(3.0 MW, 90.0 m)
30th 53 ° 59 ′ 0 ″ N, 3 ° 17 ′ 0 ″ W. in operation 2006
Burbo Bank *
(Phase 1)
90 Siemens SWT-3.6-107
(3.6 MW, 107.0 m)
25th 53 ° 29 ′ 17 "N, 3 ° 11 ′ 13" W. in operation 2007
Rhyl flats 90 Siemens SWT-3.6-107
(3.6 MW, 107.0 m)
25th 53 ° 23 ′ 16 ″ N, 3 ° 40 ′ 15 ″ W. in operation 2009
Robin Rigg 180 Vestas V90-3.0
(3.0 MW, 90.0 m)
60 54 ° 45 ′ 0 ″ N, 3 ° 43 ′ 0 ″ W. in operation 2010
Ormonde 152.4 REpower 5M
(5.08 MW, 126.5 m)
30th 54 ° 6 ′ 0 ″ N, 3 ° 24 ′ 0 ″ W. in operation 2011
Walney
(Phases 1 and 2)
367 51 × Siemens SWT-3.6-107
(3.6 MW, 107.0 m)
51 × Siemens SWT-3.6-120
(3.6 MW, 120.0 m)
102 54 ° 2 ′ 38 "N, 3 ° 31 ′ 19" W. in operation 2011
West of Duddon Sands 389 Siemens SWT-3.6-120
(3.6 MW, 120.0 m)
108 53 ° 59 ′ 2 ″ N, 3 ° 27 ′ 50 ″ W. in operation 2014
Gwynt y Môr 576 Siemens SWT-3.6-107
(3.6 MW, 107.0 m)
160 53 ° 27 ′ 0 ″ N, 3 ° 35 ′ 0 ″ W. in operation 2015 official commissioning in June 2015, first turbines since August 2013
Burbo Bank
(Phase 2)
256 MHI Vestas V164-8.0 MW
(8.0 MW, 164.0 m)
32 53 ° 28 ′ 59 "N, 3 ° 16 ′ 23" W. in operation 2017
Walney
(Phases 3 and 4)
659 40 × MHI Vestas V164-8.0 MW
(8.25 MW, 164.0 m)
47 × Siemens SWT-7.0-154
(7.0 MW, 154.0 m)
87 54 ° 5 ′ 13 ″ N, 3 ° 44 ′ 13 ″ W. in operation 2018
North Sea
Blyth * 4th Vestas V66-2.0
(2.0 MW, 66.0 m)
2 55 ° 8 ′ 10 ″ N, 1 ° 29 ′ 24 ″ W. Out of service 2000 dismantled in April 2019
Scroby Sands * 60 Vestas V80-2.0
(2.0 MW, 80.0 m)
30th 52 ° 38 ′ 42 "N, 1 ° 47 ′ 13" E in operation 2004
Kentish Flats
(Phase 1)
90 Vestas V90-3.0
(3.0 MW, 90.0 m)
30th 51 ° 27 '36 "N, 1 ° 5' 24" E in operation 2005
Beatrice
(demonstrator)
10.16 REpower 5M
(5.08 MW, 126.5 m)
2 58 ° 5 ′ 53 "N, 3 ° 4 ′ 41" W. in operation 2007
Lynn and Inner Dowsing * 194 Siemens SWT-3.6-107
(3.6 MW, 107.0 m)
54 53 ° 8 ′ 10 ″ N, 0 ° 27 ′ 29 ″ E in operation 2008
Thanet 300 Vestas V90-3.0
(3.0 MW, 90.0 m)
100 51 ° 25 ′ 30 ″ N, 1 ° 37 ′ 3 ″ E in operation 2010
Sheringham Shoal 317 Siemens SWT-3.6-107
(3.6 MW, 107.0 m)
88 53 ° 8 ′ 6 "N, 1 ° 8 ′ 49" E in operation 2011
Greater Gabbard 504 Siemens SWT-3.6-107
(3.6 MW, 107.0 m)
140 51 ° 52 '48 "N, 1 ° 56" 24 "E in operation 2012
London Array
(Phase 1)
630 Siemens SWT-3.6-120
(3.6 MW, 120.0 m)
175 51 ° 38 ′ 0 ″ N, 1 ° 33 ′ 0 ″ E in operation 2012
Lincs 270 Siemens SWT-3.6-120
(3.6 MW, 120.0 m)
75 53 ° 11 ′ 0 ″ N, 0 ° 29 ′ 0 ″ E in operation 2013
Teesside * 62 Siemens SWT-2.3-93
(2.3 MW, 93.0 m)
27 54 ° 39 ′ 0 ″ N, 1 ° 6 ′ 0 ″ W. in operation 2013
Gunfleet Sands
(Phases 1-3)
184 48 × Siemens SWT-3.6-107
(3.6 MW, 107.0 m)
2 × Siemens SWT-6.0-120
(6.0 MW, 120.0 m)
50 51 ° 43 '48 "N, 1 ° 13' 44" E in operation 2013
Humber Gateway 219 Vestas V112-3.0
(3.0 MW, 112.0 m)
73 53 ° 38 ′ 38 "N, 0 ° 17 ′ 35" E in operation 2015
Westermost Rough 210 Siemens SWT-6.0-154
(6.0 MW, 154.0 m)
35 53 ° 48 ′ 18 "N, 0 ° 8 ′ 56" E in operation 2015
Kentish Flats
(Phase 2)
49.5 Vestas V112-3.3
(3.3 MW, 112.0 m)
15th 51 ° 27 '36 "N, 1 ° 5' 24" E in operation 2016
Dudgeon 402 Siemens SWT-6.0-154
(6.0 MW, 154.0 m)
67 53 ° 16 ′ 0 ″ N, 1 ° 23 ′ 0 ″ E in operation 2017
Aberdeen Bay 93.2

9 × MHI Vestas V164-8.0 MW
(8.4 MW, 164.0 m)
2 × MHI Vestas V164-8.0 MW
(8.8 MW, 164.0 m)

11 57 ° 13 ′ 30 ″ N, 1 ° 59 ′ 35 ″ W. in operation 2018
European Offshore Wind Deployment Center (EOWDC)
Blyth
(demonstrator)
41.5 MHI Vestas V164-8.0 MW
(8.3 MW, 164.0 m)
5 55 ° 9 ′ 58 ″ N, 1 ° 22 ′ 8 ″ W. in operation 2018
Galloper 352.8 Siemens SWT-6.0-154
(6.3 MW, 154.0 m)
56 51 ° 53 ′ 31 ″ N, 2 ° 2 ′ 2 ″ E in operation 2018
Race Bank 573.3 Siemens SWT-6.0-154
(6.3 MW, 154.0 m)
91 53 ° 16 ′ 33 "N, 0 ° 50 ′ 27" E in operation 2018
Beatrice 588 Siemens SWT-7.0-154
(7.0 MW, 154.0 m)
84 58 ° 15 ′ 14 "N, 2 ° 50 ′ 38" W. in operation 2019
Hornsea
(Project One)
1218 Siemens SWT-7.0-154
(7.0 MW, 154.0 m)
174 53 ° 53 ′ 6 "N, 1 ° 47 ′ 28" E in operation 2020
East Anglia ONE 714 Siemens SWT-7.0-154
(7.0 MW, 154.0 m)
102 52 ° 14 ′ 2 "N, 2 ° 28 ′ 40" E in partial operation (2020) April 29, 2020: all turbines installed
Triton Knoll 855 MHI Vestas V164-9.5 MW
(9.5 MW, 164.0 m)
90 53 ° 28 ′ 44 "N, 0 ° 50 ′ 13" E under construction (2021) January 22, 2020: 1 of 90 foundations installed
Hornsea
(Project Two)
1386 Siemens Gamesa SG 8.0-167 DD
(8.4 MW, 167.0 m)
165 53 ° 56 '24 "N, 1 ° 41' 13" E in preparation (2022) September 11, 2017: final investment decision made
Moray Firth
(Eastern Development Area)
950 MHI Vestas V164-9.5 MW
(9.5 MW, 164.0 m)
100 58 ° 11 '17 "N, 2 ° 43' 12" W. in preparation (2022) December 6, 2018: final investment decision made; Construction scheduled to start in 2020
Neart na Gaoithe 453.6 Siemens Gamesa SG 8.0-167 DD
(8.4 MW, 167.0 m)
54 56 ° 16 ′ 5 ″ N, 2 ° 15 ′ 0 ″ W. in preparation (2023) November 28, 2019: final investment decision made, construction scheduled to start in 2021
Dogger Bank A 1200 GE Haliade-X 12 MW
(12.0 MW, 218.0 m)
100 54 ° 46 ′ 8 "N, 1 ° 54 ′ 29" E in planning (2023) September 20, 2019: Equinor and SSE won the tender
Forthwind *
(demonstrator)
12 2-B Energy 2B6
(6.0 MW, 140.6 m)
2 56 ° 10 ′ 5 ″ N, 3 ° 0 ′ 50 ″ W. in planning (2023) September 20, 2019: CIERCO wins tender
Dogger Bank B. 1200 GE Haliade-X 12 MW
(12.0 MW, 218.0 m)
100 54 ° 58 ′ 37 "N, 1 ° 40 ′ 44" E in planning (2024) September 20, 2019: Equinor and SSE won the tender
Seagreen
(phase 1)
1083 MHI Vestas V174-9.5 MW
(9.5 MW, 174.0 m)
114 56 ° 35 ′ 31 "N, 1 ° 44 ′ 28" W. in planning (2024) September 20, 2019: SSE wins tender for 454 MW
Dogger Bank C. 1200 GE Haliade-X 12 MW
(12.0 MW, 218.0 m)
100 55 ° 2 ′ 20 "N, 2 ° 49 ′ 19" E in planning (2025) September 20, 2019: Equinor and SSE won the tender
Sofia 1400 54 ° 59 ′ 20 "N, 2 ° 13 ′ 41" E in planning (2025) September 20, 2019: Innogy wins tender; final investment decision planned for spring 2021, start of construction planned for 2022
East Anglia Hub 3100 52 ° 39 '50 "N, 2 ° 50' 46" E in planning (2026) Construction scheduled to start in 2022
Hornsea
(Project Three)
2400 Siemens 53 ° 52 ′ 23 "N, 2 ° 32 ′ 13" E in planning
Hornsea
(Project Four)
1000 Siemens 54 ° 2 ′ 17 ″ N, 1 ° 16 ′ 16 ″ E in planning
Norfolk Boreas 1800 53 ° 2 ′ 24 ″ N, 2 ° 56 ′ 2 ″ E in planning
Norfolk Vanguard 1800 52 ° 52 ′ 5 "N, 2 ° 41 ′ 17" E in planning
Seagreen
(Phase 2 - Charlie and Delta)
1820 56 ° 22 ′ 12 ″ N, 1 ° 31 ′ 16 ″ W. in planning
Seagreen
(Phase 3 - Foxtrot and Golf)
1200 56 ° 22 ′ 19 ″ N, 1 ° 45 ′ 25 ″ W. in planning

See also

Individual evidence

  1. ^ First UK Offshore Wind Farm Disappears from Horizon . In: offshoreWIND.biz , April 24, 2019, accessed April 25, 2019
  2. Aberdeen 'turbocharges' offshore . In: reNEWS.biz , September 7, 2018, accessed on September 7, 2018
  3. ^ Vattenfall to build a wind farm off Aberdeen. vattenfall.com, accessed on July 21, 2016 (English).
  4. ^ All 102 Wind Turbines Installed at East Anglia ONE . In: offshoreWIND.biz , April 29, 2020, accessed on April 29, 2020
  5. ^ First Foundation In at Triton Knoll . In: offshoreWIND.biz , January 22, 2020, accessed on January 22, 2020
  6. DONG Reaches FID for World's Biggest Offshore Wind Farm . In: offshoreWIND.biz , September 11, 2017, accessed on September 11, 2017
  7. Contracts confirmed as Moray East reaches FID . In: Offshore Wind Journal - owjonline.com , December 6, 2018, accessed December 6, 2018
  8. EDF reaches financial close on 450MW Neart . In: reNEWS.biz , October 16, 2018, accessed on October 16, 2018
  9. Mainstream Puts Neart na Gaoithe on Fast Track . In: offshoreWIND.biz , May 16, 2017, accessed on May 16, 2017
  10. Breaking: UK Offshore Wind Strike Prices Slide Down to GBP 39.65 / MWh . In: offshoreWIND.biz , September 20, 2019, accessed on September 20, 2019
  11. Breaking: UK Offshore Wind Strike Prices Slide Down to GBP 39.65 / MWh . In: offshoreWIND.biz , September 20, 2019, accessed October 8, 2019
  12. Breaking: UK Offshore Wind Strike Prices Slide Down to GBP 39.65 / MWh . In: offshoreWIND.biz , September 20, 2019, accessed on September 20, 2019
  13. Breaking: UK Offshore Wind Strike Prices Slide Down to GBP 39.65 / MWh . In: offshoreWIND.biz , September 20, 2019, accessed October 8, 2019
  14. Breaking: UK Offshore Wind Strike Prices Slide Down to GBP 39.65 / MWh . In: offshoreWIND.biz , September 20, 2019, accessed on September 20, 2019
  15. Breaking: UK Offshore Wind Strike Prices Slide Down to GBP 39.65 / MWh . In: offshoreWIND.biz , September 20, 2019, accessed on September 20, 2019
  16. Innogy: Sofia FID in Early 2021 . In: offshoreWIND.biz , March 23, 2020, accessed on March 23, 2020
  17. ^ ScottishPower Renewables Bundles East Anglia Offshore Wind Trio . In: offshoreWIND.biz , November 26, 2019, accessed on November 26, 2019