Offshore HVDC systems

from Wikipedia, the free encyclopedia

Offshore HVDC systems are systems for high-voltage direct current transmission of the electricity generated from offshore wind farms to land. They are used for low-loss electrical energy transmission and have so far only been used in Germany ( North Sea ) for this purpose , as here offshore wind farms (OWP), in contrast to Great Britain and Denmark, are usually built outside of the field of vision of the coast, and therefore have to cover greater distances are. It is to be expected that this technology will also be used in other countries if the locations close to the coast are occupied here. Outside of Germany are offshore HVDC systems and for the supply of oil and gas platforms in use, for example Troll A .

Structure and functionality

Since the distances to the coast are 30 to 120 km, depending on the location of the wind farm, the three-phase transmission in the submarine cables results in large losses due to the capacitance . For this reason, so-called converter platforms are set up near the offshore wind farms - usually by the responsible transmission system operator - on which the three-phase alternating current is converted into direct current . Offshore HVDC systems are complex to set up, but reduce the transmission losses of the cables over the great distance considerably, since the capacitance of the submarine cable is irrelevant for direct current .

Offshore HVDC systems consist of a converter station built on the platform to convert the three-phase current into direct current, the HVDC submarine cable and a converter station on land. The latter converts the electricity back into three-phase current and enables it to be fed into the network . In the offshore sector, this HVDC technology was new territory, only a few companies ( Siemens , ABB , Alstom ) have had experience with this technology.

The Nordic Yards shipyards in Mecklenburg-Western Pomerania built several offshore HVDC platforms that were equipped by Siemens. Depending on the output, the fully equipped HVDC platforms weigh 2,500 to 10,000 tons.

The effort involved in planning and setting up offshore wind energy as a complete system is more complex and time-consuming than the previous HVDC systems on land. This aspect was underestimated by everyone involved, including the energy supply companies and the politicians of the states and the federal government. Therefore, the infrastructure for power transmission on land is not on schedule and the expansion of offshore wind farms is stalling due to late connection dates and offshore HVDC systems.

HVDC systems in the German Bight (bold black lines)

Offshore HVDC systems in the German Bight of the North Sea

Most of the German offshore wind farms in the North Sea are located in the German Exclusive Economic Zone (EEZ), which is at least twelve nautical miles from the coast. The wind farms consist of 40 to 120 wind turbines, the internal cable network in the wind farm (33 kV) and a transformer platform to increase the voltage to 150 to 320 kV. The prevailing water depths of 20 to 40 m here require foundations made of steel pipes ( monopiles ), tripods or half-timbered structures ( jackets ) with a weight of up to 900 t to ensure that the wind turbines stand securely . Due to the large distances between the wind farms and the onshore feed-in stations, HVDC systems (offshore high-voltage direct current transmission ) are used for low-loss energy transmission .

The HVDC BorWin 1 is the world's first high-voltage direct current transmission connection for connecting offshore structures. It is used to connect the first commercial German offshore wind farm " BARD Offshore 1 " to the German high-voltage network and thus also to the European network .

The offshore HVDC plants in the German Bight of the North Sea are grouped together.

Cluster Surname Offshore platform Network operator Substation
on land
Wind farm (s) Length of submarine cable Length of underground cable tension Transmission
capacity
status Commissioning
(Year)
Manufacturer Remarks
BorWin
( Borkum )
NOR-6-1
BorWin1
BorWin alpha Tennet TSO Hall
(at hall )
BARD Offshore 1 (400 MW) 125 km 75 km 150 kV 400 MW in operation 2013 FIG
NOR-6-2
BorWin2
BorWin beta Tennet TSO Veja Mate (400 MW)
Albatros (116.8 MW)
German Bight (269 MW)
125 km 75 km 300 kV 800 MW in operation 2015 Siemens
NOR-8-1
BorWin3
BorWin gamma Tennet TSO Emden / East
(near Borssum )
Global Tech I (400 MW)
High Seas (500 MW)
132 km 28 km 320 kV 900 MW in operation 2019 Siemens, Petrofac
NOR-6-3
BorWin4
BorWin delta Amprion Hanekenfähr
(at Emsland NPP )
130 km 130 km 320 kV 900 MW in planning (2029)Template: future / in 5 years NN Construction contract planned for 2024
NOR-7-1
BorWin5
BorWin epsilon Tennet TSO Garrel / Ost
(near Cloppenburg )
He Dreiht (900 MW) 120 km 110 km 320 kV 900 MW planned (2025)Template: future / in 5 years Siemens, Dragados August 11, 2020: Construction contract awarded
NOR-7-2
BorWin6
BorWin kappa Tennet TSO Büttel
(near Büttel )
180 km 30 km 320 kV 930 MW in planning (2027)Template: future / in 5 years NN Construction contract planned for 2022
DolWin
( Dollart )
NOR-2-2
DolWin1
DolWin alpha Tennet TSO Dörpen / West
(near Heede )
Trianel Windpark Borkum  1 (200 MW)
Trianel Windpark Borkum  2 (203 MW)
Borkum Riffgrund 1 (314 MW)
75 km 90 km 320 kV 800 MW in operation 2015 FIG
NOR-3-1
DolWin2
DolWin beta Tennet TSO Gode ​​Wind 1 (330 MW)
Gode ​​Wind 2 (252 MW)
Nordsee One (332 MW)
45 km 90 km 320 kV 916 MW in operation 2017 Aibel, FIG
NOR-2-3
DolWin3
DolWin gamma Tennet TSO Borkum Riffgrund 2 (448 MW)
Merkur (396 MW)
83 km 79 km 320 kV 900 MW in operation 2019 General Electric
NOR-3-2
DolWin4
DolWin delta Amprion Hanekenfähr
(at Emsland NPP )
60 km 130 km 320 kV 900 MW in planning (2028)Template: future / in 5 years NN Construction contract planned for 2023
NOR-1-1
DolWin5
DolWin epsilon Tennet TSO Emden / East
(near Borssum )
Borkum Riffgrund 3 (900 MW) 100 km 30 km 900 MW planned (2024)Template: future / in 4 years Aibel, ABB , Keppel FELS May 7, 2019: Construction contract awarded
NOR-3-3
DolWin6
DolWin kappa Tennet TSO Gode ​​Wind 3 (242 MW) 45 km 45 km 320 kV 900 MW under construction (2023) Siemens, Dragados July 17, 2017: Construction contract awarded
HelWin
( Helgoland )
NOR-4-1
HelWin1
HelWin alpha Tennet TSO Büttel
(near Büttel )
Sea wind south / east (288 MW)
North Sea east (295 MW)
85 km 45 km 250 kV 576 MW in operation 2015 Siemens
NOR-4-2
HelWin2
HelWin beta Tennet TSO Amrumbank West (302 MW)
Kaskasi (342 MW)
85 km 45 km 320 kV 690 MW in operation 2015 Siemens
SylWin
( Sylt )
NOR-5-1
SylWin1
SylWin alpha Tennet TSO Butendiek (288 MW)
DanTysk (288 MW)
Sandbank 1 (288 MW)
160 km 45 km 320 kV 864 MW in operation 2015 Siemens
SylWin2 SylWin beta Tennet TSO 536 MW Abandoned planning (2025)Template: future / in 5 years NN No wind farm authorized to connect
BalWin ( Baltrum ) NOR-9-1
BalWin1
BalWin alpha Tennet TSO Unterweser
(at Unterweser NPP )
140 km 80 km 525 kV 2,000 MW in planning (2029)Template: future / in 5 years NN Construction contract planned for 2024
NOR-9-2
BalWin2
Amprion Search area Ibbenbüren / Mettingen / Westerkappeln unconfirmed NN
NOR-10-2
BalWin3
Tennet TSO Heide / West
(near Heide )
unconfirmed NN
NOR-10-1
BalWin4
Tennet TSO Unterweser
(at Unterweser NPP )
150 km 80 km 525 kV 1,700 MW in planning (2030)Template: future / in 5 years NN Construction contract planned for 2025
LanWin ( Langeoog ) NOR-12-1
LanWin1
Tennet TSO Wilhelmshaven 2
(near Wilhelmshaven )
170 km 50 km 525 kV 2,000 MW in planning (2030)Template: future / in 5 years NN
NOR-12-2
LanWin2
Amprion Wehrendorf
(near Wehrendorf )
unconfirmed NN
NOR-11-1
LanWin3
Westerkappeln
(near Westerkappeln )
160 km 160 km 525 kV 2,000 MW in planning (after 2030)Template: future / in 5 years NN
NOR-11-2
LanWin4
Wehrendorf
(near Wehrendorf )
170 km 160 km 525 kV 2,000 MW in planning (after 2030)Template: future / in 5 years NN
NOR-13-1
LanWin5
Tennet TSO Heide / West
(near Heide )
525 kV 2,000 MW in planning (after 2030)Template: future / in 5 years NN

Source: Network development plan of the transmission system operator , confirmed by the Federal Network Agency .

See also

Web links

literature

  • Andreas Rosponi, Reiner Klatte, Klaas Oltmann, Jan Henning Günther: The MOAB platform concept and its application for transformer stations within offshore wind farms , design examples and plans, yearbook of the Schiffbautechnische Gesellschaft 2010

Individual evidence

  1. TenneT BorWin1. Retrieved May 7, 2019 .
  2. ^ ABB BorWin1. Retrieved May 7, 2019 .
  3. TenneT BorWin2. Retrieved May 7, 2019 .
  4. TenneT BorWin3. Retrieved May 7, 2019 .
  5. Michael Müller: 12,000 tons for the energy transition. In: Daily port report of April 30, 2014, p. 1
  6. Sariana Kunze: TenneT awards major order for North Sea network connection. Vogel Communications Group , accessed April 24, 2014 .
  7. TenneT BorWin5. Retrieved August 16, 2020 .
  8. Tennet significantly reduces costs with BorWin5 offshore connection. Retrieved August 11, 2020 .
  9. TenneT DolWin1. Retrieved May 7, 2019 .
  10. ABB DolWin1. Retrieved May 7, 2019 .
  11. TenneT DolWin2. Retrieved May 7, 2019 .
  12. ABB DolWin2. Retrieved May 7, 2019 .
  13. TenneT DolWin3. Retrieved May 7, 2019 .
  14. Claus Gorgs: GE chases Siemens in offshore wind power - Germany's floating socket. Manager Magazin , accessed July 19, 2017 .
  15. TenneT DolWin5. Retrieved August 29, 2019 .
  16. Tennet places orders for DolWin5 and emphasizes cost reductions in offshore network connections. Retrieved May 7, 2019 .
  17. TenneT DolWin6. Retrieved May 7, 2019 .
  18. Network connection DolWin6 of the offshore wind turbine DolWin kappa by means of a 600 kV direct current line. Retrieved July 30, 2017 .
  19. Tennet awards Siemens the contract for DolWin6. Retrieved July 18, 2017 .
  20. TenneT HelWin1. Retrieved May 7, 2019 .
  21. TenneT HelWin2. Retrieved May 7, 2019 .
  22. TenneT SylWin1. Retrieved May 7, 2019 .
  23. Confirmation of the electricity network development plan for the target year 2030. (PDF) Federal Network Agency , December 2019, accessed on January 20, 2020 .