Hanover – Minden railway line

from Wikipedia, the free encyclopedia
Hanover – Minden
Route number (DB) : 1700
Course book section (DB) : 370
Route length: 64.4 km
Gauge : 1435 mm ( standard gauge )
Route class : D4
Power system : 15 kV 16.7 Hz  ~
Top speed: 200 km / h
Dual track : continuous
BSicon .svgBSicon STR.svgBSicon STR.svg
Hannöversche Südbahn , SFS from Kassel
BSicon STR + r.svgBSicon STR.svgBSicon STR.svg
Route from Lehrte
BSicon S + BHF.svgBSicon BHF.svgBSicon SBHF.svg
0.0 Hannover Hbf
BSicon ABZg + l.svgBSicon STRr + l.svgBSicon ABZgr.svg
BSicon STR.svgBSicon SHST.svgBSicon STR.svg
Hanover-Nordstadt
BSicon DST.svgBSicon STR.svgBSicon STR.svg
3.2 Hanover Castle (Bft)
BSicon eHST.svgBSicon STR.svgBSicon DST.svg
3.8 Hanover-Hainholz
BSicon ABZgr.svgBSicon ABZgr.svgBSicon ABZgr.svg
Route to Hamburg
BSicon STR2.svgBSicon STR3u.svgBSicon STR.svg
( Flyover structure )
BSicon STR + 1u.svgBSicon STR + 4.svgBSicon STR.svg
BSicon SHST.svgBSicon eBHF.svgBSicon STR.svg
5.5 Hanover-Leinhausen
BSicon STR.svgBSicon STR.svgBSicon BST.svg
6.0 Hanover curve ( Abzw )
BSicon hKRZWae.svgBSicon hKRZWae.svgBSicon hKRZWae.svg
6.1 rope
BSicon STR.svgBSicon STR.svgBSicon ABZgl.svg
6.2 to the Seelze – Lehrte freight bypass
BSicon STR.svgBSicon BST.svgBSicon BST.svg
7.1 Letter (Abzw)
BSicon STR.svgBSicon STR.svgBSicon ABZg + l.svg
Lehrte freight bypass
BSicon SHST.svgBSicon eHST.svgBSicon STR.svg
7.9 Letter
BSicon STR.svgBSicon STR.svgBSicon DST.svg
9.1 Seelze Rbf
BSicon STR.svgBSicon STR.svgBSicon BST.svg
10.4 Seelze Rbf West
BSicon SBHF.svgBSicon BHF.svgBSicon STR.svg
11.1 Seelze
BSicon STRl.svgBSicon ABZg + r.svgBSicon STR.svg
(End of the S-Bahn line)
BSicon .svgBSicon hKRZWae.svgBSicon hKRZWae.svg
13.3 Mittelland Canal
BSicon .svgBSicon SHST.svgBSicon STR.svg
16.3 Dedensen - Gümmer
BSicon .svgBSicon SBRÜCKE.svgBSicon SBRÜCKE.svg
A 2
BSicon .svgBSicon STR.svgBSicon BST.svg
Seelze Gümmerwald (Abzw)
BSicon STR + l.svgBSicon KRZu.svgBSicon ABZgr.svg
(Flyover structure)
BSicon DST.svgBSicon S + BHF.svgBSicon DST.svg
21.4 Wunstorf ( wedge station )
BSicon STRr.svgBSicon ABZgr + l.svgBSicon STRr.svg
Route to Bremen
   
Düendorf (towards Minden until 1968)
   
Mittelland Canal
S-Bahn station
28.3 Haste (Han)
   
28,595 Waldstrasse L 449
   
Deisterbahn to Weetzen
   
29,580 To the forest
   
29,877 Main street K 50
Station without passenger traffic
31.2 Rehren
S-Bahn stop ...
35.7 Lindhorst
Station without passenger traffic
36.1 Lindhorst (formerly Bf)
S-Bahn station
43.0 Stadthagen
   
Route to Rinteln
   
former route to Leese - Stolzenau
   
Former route Stadthagen – Stolzenau
S-Bahn stop ...
48.4 Kirchhorsten
   
formerly Bad Eilsener Kleinbahn
S-Bahn station
55.2 Buckeburg
   
formerly Bad Eilsener Kleinbahn
   
58.9 Evesen
   
State border Lower Saxony / North Rhine-Westphalia
BSicon dSTR2h + r.svgBSicon BS2lr.svgBSicon dBS2c3.svg
Line from Nienburg
BSicon KRZu.svgBSicon KRZu.svg
Mindener Kreisbahnen
BSicon DST.svgBSicon DST.svg
63.0 Minden (Westf) Gbf
BSicon DST.svgBSicon S + BHF.svg
64.4 Minden (Westf) Pbf ( Inselbahnhof )
BSicon STR.svgBSicon STR.svg
Main line to Hamm

Swell:

The Hanover – Minden railway line is one of the most important railway lines in Lower Saxony and Germany . It connects the Lower Saxony state capital Hanover via Wunstorf , Stadthagen and Bückeburg with Minden , Osnabrück , Amsterdam and the Ruhr area . On the Seelze – Wunstorf section, the line runs parallel to the Hanover freight bypass .

history

Construction and operation

The line was opened on October 15, 1847 by the Royal Hanover State Railways ; it mainly opened up the Principality of Schaumburg-Lippe and its residential city of Bückeburg and established a continuous connection from Hanover to the Rhineland. On December 12, 1847, the Wunstorf – Bremen railway line branching off at what was then the Wunstorf island station was opened. Since then, it has also been one of the most important railway lines in Germany in its entire history, as it connects the ports of Bremen with southern Germany . Other connecting and connecting lines are or were the railway town of Hagen-Stolzenau , the railway Nienburg-Minden , the Cologne-Minden trunk line as a continuation of the route to the Rhineland, the railway Rinteln-Stadthagen , the Minden Museum Railway and the Bad Eilsener Small train from Bückeburg to Bad Eilsen and briefly via the suburb of Meißen to Minden .

With the reorganization of the traffic after reunification, this east-west railway line is one of the most heavily used railway lines of Deutsche Bahn (more than 100,000 trains in 2005).

The route between Wunstorf and Minden has been classified as an " congested railroad " since 2012 .

Accidents

On September 6, 1923, following the mistake of a block attendant, the D  10 from Berlin to Cologne at Seelze-Lohnde on the holding D 138 from Leipzig to Amsterdam. 18 people died and 19 were injured.

On January 4, 1943, the engine driver of the SFR  2304 in front of Wunstorf failed to see a signal indicating a “stop” during a heavy snowstorm and drove onto the D 8. 25 people died and 169 others were injured. Lower Saxony's economic and transport manager Kurt Finkenwirth was one of the fatalities .

On May 19, 2016, an ICE between Wunstorf and Haste collided with an eruption on the wing rail of a test frog that had not withstood the dynamic loads of rail operations. There was property damage to infrastructure and vehicles.

expansion

Expansion to the high-speed route

The first Federal Transport Infrastructure Plan (1973) introduced the upgraded line Dortmund, Hanover and Braunschweig as a scheduled eight expansion projects in the field of railways. The project was also included in the 1980 Federal Transport Infrastructure Plan.

In 1984, operations began in a 23.5-kilometer section between Bückeburg and Haste at a scheduled speed of 200 km / h. In 1985 a 13.0 kilometer section between Hanover and Wunstorf followed. This means that the 6.9 km long section between Haste and Wunstorf is not designed for 200 km / h.

New Bielefeld – Hanover line

A new high-speed line from Bielefeld to Hanover is to run largely along federal motorway 2 and be accessible at 300 km / h. It is necessary to implement the Germany cycle as part of the Federal Transport Infrastructure Plan 2030 .

Expansion of the Wunstorf - Minden bottleneck

The axis between Wunstorf and Minden has not yet been expanded to four tracks.

history

After the completion of the expansion of the Minden - Hamm line, further construction was planned as early as the 1920s. Only with reunification did the route come into focus again. In the Federal Railways Expansion Act of November 15, 1993, the line was mentioned as a new measure in urgent need . The expansion was mentioned again in the 2003 Federal Transport Infrastructure Plan. The investment master plan published in 2007 for the federal transport infrastructure up to 2010 did not include an expansion. In the demand plan review published in November 2010, the expansion was postponed due to a benefit-cost ratio of less than 1. Under these conditions, the route extension was not eligible for funding. Instead, traffic should develop on the Löhne – Hildesheim – Braunschweig routes . Against this decision there was a resolution of the regional council of the Detmold district government , which expected the route expansion to be taken into account in the Federal Transport Infrastructure Plan 2030 .

In 2010, the federal government estimated the construction costs according to the Federal Transport Infrastructure Plan 2003 for the four-track expansion of around 900 million euros.

The draft of the Federal Transport Infrastructure Plan 2030 included a new double-track line between Letter and Lindhorst, from there an extension by two more tracks to Echtorf and a new line between Echtorf and Porta Westfalica including a tunnel through Jakobsberg. Between Porta Westfalica and Letter, the new tracks were to be designed for 230 km / h, the Porta-Westfalica - Löhne section for a maximum of 180 km / h. This should save 10 minutes.

planning

A four-track expansion of the line, as on the connecting Hamm – Minden railway to the west, is still planned. However, it is still controversial whether the existing route should be expanded continuously or whether Wunstorf should be bypassed with a new line from Seelze to Haste, west of Haste the existing line is to be expanded. In the Third Act on the Amendment of the Federal Railways Expansion Act of 23 December 2016, the expansion is included as No. 13 in Urgent Need , but not reported as a bottleneck removal. The following is noted: "Without the Seelze-Süd crossing and without the Jakobsberg tunnel, provided that the shortened travel time of eight minutes required for a German cycle is expected."

In its regional spatial planning program, the Hanover region has determined to expand the Seelze - Wunstorf section to improve the overall range of S-Bahn services. The financing is still unclear.

Transport offer

Intercity Express , Intercity , Regional Express trains and S-Bahn trains run along the entire continuously electrified route . There is also a dense freight traffic . RE trains (Braunschweig - Bielefeld or Rheine) run every hour between Minden and Hanover as railcars operated by the Westfalenbahn railway company and S-Bahn trains on the S1 line (Haste-Hanover-Minden). In the Wunstorf – Hannover section, the S-Bahn traffic is concentrated by the S2 Haste – Hannover – Nienburg line . This route is also used by RE trains on the Hanover - Bremen - Norddeich Mole line.

Between Haste and Hanover the tariff of the Greater Hanover Transport (GVH) applies, the district of Schaumburg is connected to the GVH via a special time card tariff.

The line has six tracks in the Hanover-Nordstadt – Seelze area, four-track between Hanover Hbf and Hanover-Nordstadt with separate S-Bahn tracks, four-track between Seelze and Wunstorf through shared use of the freight bypass, and two-track in the Wunstorf – Minden area. In this area, freight traffic must therefore repeatedly turn to the sidings in order to allow faster passenger trains to pass.

literature

  • Matthias Blazek: The Grafschaft Schaumburg 1647–1977. ibidem, Stuttgart 2011, ISBN 978-3-8382-0257-0 , pp. 54-63. (The history of the Hanover – Minden railway line)

Individual evidence

  1. DB Netze - Infrastructure Register
  2. Railway Atlas Germany . 9th edition. Schweers + Wall, Aachen 2014, ISBN 978-3-89494-145-1 .
  3. Resolution of the regional council of the Detmold administrative district to include the Minden – Haste / expansion or new Haste – Seelze rail line in the 2025 target network of the Federal Minister for Transport, Building and Urban Development. In: Mindener Tageblatt . March 29, 2011, accessed April 11, 2011 (PDF; 54 KiB).
  4. fahrweg.dbnetze.com ( Memento of the original dated August 28, 2017 in the Internet Archive ) Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice.  @1@ 2Template: Webachiv / IABot / fahrweg.dbnetze.com
  5. ^ Hans Joachim Ritzau: Railway disasters in Germany. Splinters of German history . Volume 1, Landsberg-Pürgen 1979, ISBN 3-921304-38-6 , p. 92.
  6. ^ Hans Joachim Ritzau: Railway disasters in Germany. Splinters of German history . Volume 1, Landsberg-Pürgen 1979, p. 93.
  7. Waldemar R. Röhrbein : Finkenwirth, Kurt. In: Dirk Böttcher , Klaus Mlynek, Waldemar R. Röhrbein, Hugo Thielen : Hannoversches Biographisches Lexikon . From the beginning to the present. Schlütersche, Hannover 2002, ISBN 3-87706-706-9 , p. 117. ( online via Google books )
  8. Interim report . (PDF) Dangerous event in railway operations. In: eisenbahn-unterfalluntersprüfung.de. Federal Agency for Railway Accident Investigation, May 13, 2020, p. 2 , accessed on May 30, 2020 .
  9. ^ Rüdiger Block: On New Paths. The new lines of the Deutsche Bundesbahn. In: Eisenbahn-Kurier Special: High-speed traffic . No. 21, 1991, excluding ISSN, pp. 30-35.
  10. Christian Woelker: Federal Transport Infrastructure Plan '80: The rail is catching up. In: Wolfgang Vaerst , Peter Koch (eds.): Yearbook of the Railway System, Volume 31, Hestra-Verlag, Darmstadt 1980, ISBN 3-7771-0160-5 , pp. 30-36.
  11. ^ Rüdiger Block: ICE racetrack: the new lines. In: Eisenbahn-Kurier Special: High-speed traffic . No. 21, 1991, excluding ISSN, pp. 36-45.
  12. ^ New line Bielefeld - Hanover and high-speed line Bielefeld - Hamm. Retrieved October 7, 2019 .
  13. Law on the expansion of federal railways (Federal Railways Expansion Act) ( PDF version ) accessed on January 6, 2011.
  14. Investment framework plan up to 2010 from 2007 (PDF) ( Memento of the original from March 14, 2012 in the Internet Archive ) Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. , accessed January 2011. @1@ 2Template: Webachiv / IABot / www.bmvbs.de
  15. Results of the review of the requirement plans for the federal railways from November 2010 (PDF) ( Memento of the original from November 21, 2010 in the Internet Archive ) Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. , accessed January 2011. @1@ 2Template: Webachiv / IABot / www.bmvbs.de
  16. Kampeter supports route resolution. In: Mindener Tagblatt. April 4, 2011, accessed April 11, 2011.
  17. Position paper of the IHK Ostwestfalen-Lippe: “Keeping connections in rail traffic” ( Memento of December 24, 2013 in the Internet Archive ) (PDF; 746 KiB)
  18. Referent draft of the Federal Transport Infrastructure Plan 2030 ( PDF ( Memento of the original from March 16, 2016 in the Internet Archive ) Info: The archive link has been inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this note. , P. 169f ) @1@ 2Template: Webachiv / IABot / init.pro.contentstream.de
  19. Billion tunnel planned for the train through the Weser Mountains. on: nw.de , March 19, 2016.