Biblis nuclear power plant

from Wikipedia, the free encyclopedia
Biblis nuclear power plant
General view of the facility from the left bank of the Rhine
General view of the facility from the left bank of the Rhine
location
Biblis nuclear power plant (Hesse)
Biblis nuclear power plant
Coordinates 49 ° 42 '36 "  N , 8 ° 24' 55"  E Coordinates: 49 ° 42 '36 "  N , 8 ° 24' 55"  E
Country: GermanyGermany Germany
Data
Owner: RWE
Operator: RWE Power
Project start: 1969
Commercial operation: Feb. 26, 1975
Shutdown: March 18, 2011

Decommissioned reactors (gross):

2 (2,525 MW)

Planning set (gross):

2 (2,690 MW)
Energy fed in in 2009: 2524.3 GWh
Energy fed in since commissioning: 461,971.262 GWh
Website: Page at RWE
Was standing: December 31, 2009
The data source of the respective entries can be found in the documentation .
f1

The shutdown Biblis nuclear power plant (KWB) is located in the southern Hessian community of Biblis near the confluence of the Weschnitz and the Rhine . The owner and former operator of the nuclear power plant is RWE Power AG .

The nuclear power plant Biblis delivered with two almost identical pressurized water reactors a total capacity of up to 2,525 megawatts into the power grid. Biblis was the second most profitable nuclear power plant in Germany after Gundremmingen / Bavaria. Two other initially planned blocks, Biblis C and Biblis D, were not built.

In the context of the Fukushima nuclear disaster , RWE had to shut down Block A (the older of the two reactors) on the evening of March 18, 2011 due to possible safety risks for the population. At this point in time, block B was already undergoing a scheduled overhaul, so it did not have to be taken off the grid. RWE thus followed the order of the Hessian Ministry for the Environment, Energy, Agriculture and Consumer Protection to shut down the system for three months (so-called nuclear moratorium ).

On April 1, 2011, RWE announced that it had filed a lawsuit against this order to protect the interests of the shareholders before the Hessian Administrative Court (VGH). It is assumed that a lost profit of around 1 million euros per day of standstill, for which compensation is demanded. At the end of February 2013, the Hessian VGH ruled on the basis of the continuation declaratory action that the three-month shutdown ordered after the Fukushima disaster was unlawful. The Federal Administrative Court rejected the complaints against the non-admission of the appeal in December 2013. The state of Hesse is now threatened with a claim for damages by the operator RWE. An investigative committee in the Hessian state parliament has been dealing with the decommissioning of the power plant since March 2014.

The Federal Network Agency announced on August 31, 2011 that the power plant would no longer be started up and that it would not be available as a “cold reserve”. The operator RWE announced on May 11, 2012 that it preferred direct demolition to safe enclosure and that it was making preparations. RWE Power AG applied for the decommissioning and dismantling of the Biblis power plant, units A and B, in a letter dated August 6, 2012. The two units were decommissioned on June 1, 2017, and dismantling work began immediately afterwards.

Data

Basic data

Block A

The wall thickness of the Biblis A reactor building is 60 centimeters, the exhaust chimney is 101 meters high. The reactor pressure vessel weighs 425 tons. Biblis A has two 80 meter high fan cooling towers with forced ventilation. The base diameter of a cooling tower is 68 m. Block A belongs to the 2nd generation of German pressurized water reactors and is the world's first commercially used nuclear reactor of the 1,300 MW class. It served as a model for the following generations of pressurized water systems, the pre-convoy and the convoy generation. The reactor core of Biblis A consists of 193 fuel elements with a total of around 45,000 fuel rods and around 100 tons of uranium dioxide.

As the father of block A is Henry Almond .

Block B

The wall thickness of the Biblis B reactor building is 80 centimeters, the exhaust chimney is 100 meters high. Biblis B has two 80-meter-high forced-ventilation fan cooling towers. The base diameter of a cooling tower is 69 m. As a rule, however, Unit B was operated without cooling towers. Cooling tower operation was only necessary in the case of high Rhine water temperatures or low water in order not to exceed the specified temperature limits.

Blocks C and D

A natural draft wet cooling tower with a height of 160 meters was planned for Block C and Block D. A sectional and functional model of block C is in the information center. Biblis C was planned as a convoy system. The first large components such as reactor pressure vessels and steam generators have already been manufactured. The reactor pressure vessel was later used for material tests. The reactor lid is still used today for inspection teams as a training object.

Data of the reactor blocks

The nuclear power plant has two shut down and two discarded units:

Reactor block Reactor type KWU building line electrical power thermal reactor power start of building Network synchronization Commercial operation generated energy since commissioning Shutdown
by moratorium
finally shut down
Electricity quantities from
Jan. 1, 2000
additional
quantities of electricity
net gross (TWh net)
Biblis-A Pressurized water reactor
2nd generation DWR
1,167 MW 1,225 MW 3,517 MW 01/01/1970 08/25/1974 02/26/1975 244 TWh May 30, 2011 Atomic moratorium 62.00 68.617
Biblis-B 1,240 MW 1,300 MW 3,733 MW 02/01/1972 04/25/1976 January 31, 1977 260 TWh 81.46 70.663

history

Location of the Biblis NPP on the Rhine
Block A (right), Block B (left)
Block B (left), Block A (right)
Property protection on the south side of the nuclear power plant
The return structure of Block B (Block B in the background) into the Rhine
The Biblis nuclear power plant is located on the Rhine. On the right the two cooling towers of Block A
The two cooling towers of block B, with safety systems
The two cooling towers of block A, right behind one of block B

Construction and planning

In the planning phase of the power plant, various locations were considered, including Trebur , about 35 kilometers away from the current location , but the decision was made in favor of Biblis due to the very good grid connection. Both a 220 kV and a 400 kV line are available here. The blocks are connected to both the substation in Pfungstadt and the large substation in Bürstadt .

Initially, there were hardly any critical voices against Biblis: only one citizen protested against the application for a permit for Block A. Only eight citizens raised objections to the approval of Block B, which was even more powerful with 1,300 MW, in 1971. The press, too, has been reluctant to write critical articles for years, as a study initiated by the Federal Ministry of Research in 1974 shows: In only 123 of 20,000 newspaper articles analyzed from 1970 to 74, concerns about the technology are expressed or citizens' initiatives are mentioned.

The construction costs for Biblis A were around 800 million DM, for Biblis B around one billion DM. In the seventies, two more blocks, Blocks C and D, were planned. While Biblis D was quickly discarded (planning started in 1975, planning ended in 1979), the planning for Biblis C did not end until 1995.

Installation

On July 16, 1974, the first chain reaction was initiated in block A. Block A supplied electricity to the public grid for the first time on August 25, 1974 . The nuclear commissioning ( criticality ) took place in Block B on March 25, 1976.

In 2006, an on- site interim storage facility for spent nuclear fuel elements with a heavy metal weight of 1400 tons was put into operation. It offers space for 135 castor casks with spent fuel elements. It is 92 m long, 38 m wide and 18 m high. From the outside, the building resembles an ordinary industrial hall. Seven Castor casks with radioactive waste from Sellafield are to be stored in the interim storage facility . The 85 centimeter thick outer walls and the 55 centimeter thick concrete roof reduce the radiation to such an extent that the values ​​permitted on the power plant fence are complied with. About 80 places are currently occupied.

Operating times of the power plant units

In the so-called nuclear consensus , the federal government and energy supply companies have stipulated, among other things, that all German nuclear power plants are still allowed to generate a limited amount of residual electricity, which corresponds to a standard service life of 32 years on average. For Biblis A the final shutdown was for the end of 2009, the shutdown of Biblis B was planned for 2010. Due to the flexible regulation of residual electricity volumes, the shutdown date could not be precisely predicted because every standstill (see also events of October 16, 2006) postponed the date. After the federal government withdrew the shortening of the reactor operating times in 2010 and granted the Biblis A and Biblis B units additional electricity volumes of around eight years, the units were not expected to be shut down before 2020.

With the decision of the federal government of March 14, 2011, however, a three-month nuclear moratorium on the extension of the service life was announced, so that the power plant was shut down on March 18, 2011.

On May 29, 2011, the federal government decided that both units of the Biblis nuclear power plant should not go back online. There were considerations to have Block B shut down as a “reserve power plant”, but to be able to restart it briefly in the event of electricity bottlenecks. RWE did not agree with this decision. On June 16, 2011, RWE announced that Biblis B will no longer go online.

Biblis A

In 1997 the Hessian nuclear supervisory authority initiated proceedings for the decommissioning of Biblis A due to identified safety-related problems. However, the head of the Reactor Safety and Radiation Protection Department of the Federal Environment Ministry Gerald Hennenhöfer prevented the closure of the Biblis NPP, which had already been decided by the Hessian state government, by issuing federal supervisory instructions.

The atomic consensus allowed a consent-free transfer of electricity from older plants to younger plants; A transfer from younger to older systems required the approval of the Ministry of Economic Affairs, the Ministry of the Environment and the Chancellery. In the negotiations on the nuclear phase-out for the decommissioned Mülheim-Kärlich nuclear power plant, RWE was awarded a transferable residual electricity volume of 107 TWh. Of this amount of electricity, 30 TWh could be transferred to Block B without approval. In September 2006, RWE AG submitted an application for the transfer of 30 TWh of electricity from the (younger) Mülheim-Kärlich power plant to the (older) Biblis A power plant. If this application had been approved, RWE would have operated the Biblis A power plant until the second half of 2011 and then - so the further consideration of RWE - can switch off together with Biblis B. Taking into account the shutdown due to the replacement of undercut anchors, the shutdown date mentioned would have been postponed to 2013.

This main application for Block A, submitted by RWE , was provisionally rejected by the Federal Environment Ministry in March 2007 and finally rejected in May 2007. The Ministry of the Environment represented the legal opinion that a transfer of electricity from the Mülheim-Kärlich power plant to Biblis A was not possible under the Atomic Energy Act. On April 7, 2008, the Ministry of the Environment rejected the auxiliary request for the transfer of electricity from the Emsland nuclear power plant to Biblis A, which was also submitted . The main reason given was that Biblis A had fewer safety reserves than the more modern Emsland nuclear power plant.

In April 2007, RWE Power filed a complaint with the Hessian Administrative Court in Kassel against the rejection of the main motion and also the subsidiary motion , which was dismissed. The appeal by RWE before the Federal Administrative Court in Leipzig was also rejected by decision of March 26, 2009; the rejection of longer terms also applies to the Brunsbüttel nuclear power plant .

On January 21, 2010, talks between the federal government and energy suppliers took place for the first time after the change of government in 2009 . In order to ensure provisional continued operation until the decision of the federal government, RWE bought an electricity quota of 4.8 TWh from the already decommissioned Stade nuclear power plant of the operator E.ON in May 2010 . Depending on the mode of operation, the electricity quota for Biblis A could last until 2012.

A final decision on the continued operation of the nuclear power plants was made in autumn 2010. Both blocks received an additional electricity quota in addition to the amount of electricity specified in the nuclear consensus of 2002, which corresponded to an (arithmetical) additional term of around 8 years. The additional amount of electricity for Biblis A was 68.617 TWh (net) and was thus higher than the remaining amount of electricity of 62,000 TWh (net) specified in the 2002 nuclear consensus.

In November 2011, two unsuitable fuses were discovered in the Biblis A block and replaced. Neither the functionality nor the staff were affected by this. The operating company RWE carried out a check on all, i.e. several thousand, backups. Since it was not possible to find out why these fuses were being used, tests were also carried out on the components in other nuclear power plants.

Biblis B

On September 9, 2005, the IPPNW (Doctors for the Prevention of the Nuclear War, Doctors with Social Responsibility) submitted an application to the Hessian nuclear authority to shut down the Biblis B nuclear power plant. Since this application was not granted, the IPPNW filed a lawsuit on December 12, 2008 with the Hessian Administrative Court. Accordingly, the Biblis B power plant block had at least 210 fundamental and serious safety deficiencies. The IPPNW withdrew the application for withdrawal or revocation of the operating license by letter dated March 17, 2008.

According to the nuclear consensus , RWE was allowed to transfer a residual amount of electricity of up to 21.45 TWh from Mülheim-Kärlich to Biblis B without a permit, which, according to an estimate from June 2007, meant an extension of the service life for Biblis B until 2013. In August 2010, RWE made use of this option and had 8.1 TWh transferred to Biblis B.

Post-operational phase and dismantling

Castor containers at Biblis train station for transporting nuclear waste from the Biblis nuclear power plant in November 2013

The reactors are in the post-operational phase . According to a forecast by the Hessian Ministry of the Environment, the plant is expected to be dismantled from 2016. Meanwhile, RWE is examining the option of sealing ( secure enclosure ), which would result in a much later dismantling. On June 1, 2017, RWE Power AG announced that it had taken advantage of the approval to dismantle the nuclear power plant. The dismantling work has officially started. These should last 15 years.

Since the shutdown of the Biblis nuclear power plant led to increased problems with maintaining the voltage, the transmission network operator Amprion and the power plant operator RWE Power decided to convert the synchronous generator of block A for phase shift operation in order to generate the required reactive current . The upgrade was carried out by Siemens from October 2011 to February 2012.

safety

According to the operator, the safety devices of the two power plants that were built more than 30 years ago were constantly monitored and improved. The fact that, as required by the Atomic Energy Act , protection against damage was achieved in line with the state of the art in science and technology was regularly checked by supervisory authorities and their experts. As far as material fatigue is concerned, regular tests have shown that both units could have been operated without problems for 60 years. The IAEA lists the Biblis A and B systems as a reference for successful safety retrofitting of older nuclear power plants.

A study by Greenpeace clearly contradicts this representation. Unit A of the power plant was designed and built at a time when no protective measures were taken against the crash of a military aircraft.

Another criticism is that there is no separate emergency control room outside of the reactor building, from which a reactor can be controlled even in the event of serious malfunctions in the reactor building. Since the blocks are almost identical in construction and are also connected underground, it is possible in the event of an emergency to operate the neighboring block through an emergency control room located in the respective neighboring block and, in the event of an emergency, to shut it down in a regulated manner and to ensure the removal of residual heat. The critics, however, doubt that this is still possible in the event of an incident.

In the case of an "emergency", however, it is not an incident in the sense of a primary leak, rather the entire primary circuit including the steam generator up to the relief control valves (and associated safety valves) is fully functional. The area of ​​the so-called auxiliary system building (for example, wastewater is treated here, ventilation systems are located there, etc.), the machine house, switchgear building, control room and supply wing are no longer available. In such a case, it is therefore necessary to regulate the supply of water to the steam generator and thus the cooling and borating of the primary circuit from an alternative control point. Here - and this is unique in Biblis - one can fall back on the large interrelationship of the blocks. At all other locations in Germany there are no two identical blocks (with the exception of Gundremmingen, where it is, however, boiling water systems), so that one had to rely on its own emergency control room for the construction of the systems there.

On July 15, 2009, it was announced that, after the annual report of the Federal Office for Radiation Protection (BfS) and the incident at the Krümmel nuclear power plant had been announced, Federal Environment Minister Sigmar Gabriel would retrofit closer meshed sump sieves by the operator RWE before restarting after the overhaul that has been taking place since January 2009 a sump filter backwash requested. In the event of a loss of coolant accident, it is assumed that insulating materials collect in the building sump and these could then clog the sump sieves, which ensure aftercooling. Thanks to the sump filter backwash, this can be avoided and safe after-cooling operation is guaranteed.

Various organizations critical of nuclear power repeatedly criticized the fact that there were no so-called stamp fields on at least 200 safety-relevant pipelines. The operator, as well as the TÜV had refuted this, however, and various reports confirmed that the complete documentation according to the requirements of the Atomic Energy Act was available for all safety-relevant pipelines.

radioactivity

Due to their operational nature, nuclear power plants discharge small amounts of radioactive substances (emissions) via exhaust air and wastewater. The Atomic Energy Act obliges the supervisory authorities, among other things, to monitor operations with regard to the permitted limit values. A corresponding overview for the KWB can be found on the website of the Hessian Ministry for the Environment, Energy, Agriculture and Consumer Protection.

Accidents

There have been a total of 437 (Biblis A) plus 440 (Biblis B) events that have to be reported (as of December 31, 2013).

Most of these reportable events, however, can be assigned to reporting category N, according to the INES scale 0, which means that these were events with little or no safety relevance.

  • December 17, 1987 : Employees overlooked a non-closed shut-off valve. To close the valve , a test valve was opened in jog mode . As a result, radioactive primary coolant escaped from the containment into the annulus. Since the exit of the reactor cooling water from the primary circuit took place outside the containment and thus a return from the sump via the safety feed pumps or after-cooling pumps was no longer possible, the risk of a possible meltdown was heavily discussed. The incident came to the public only after a year through an article in an American journal (Nucleonics Week) . However, the operator reported it to the authorities in good time, which did not publish a press release. After the incident became known, the Federal Environment Minister reprimanded the information policy of the operator RWE, and thousands demonstrated for the shutdown of the power plant. The incident was subsequently classified as level 1 with the introduction of the International Assessment Scale for Nuclear Events (INES), which in the assessment scheme according to INES means that the statutory emission limit values ​​are exceeded and an individual of the population is exposed to radiation beyond the statutory limit values ​​("Incident / Incident" ) means. Since this event, Biblis NPP has published every occurrence on the plant via a press officer and later on the Internet. The cost of this reportable event is estimated at $ 16 million.
  • October 3, 1989 : Parts of the emergency power rails are disconnected for 14 hours. The Hessian Ministry of the Environment announces this as a category E ('urgent') incident.
  • 23 August 1999 : reportable event of category N: coolant containing activity enters the superheated steam circuit due to a leak in the coolant cleaning system.
  • February 8, 2004 : Event of the urgent category (event no. 04/016, INES level 0: "No or only very little safety-related significance"): During full load operation, a weather-related short circuit occurred due to an unsafe covering of safety-relevant devices outside the power plant that led to the separation of the power plant block from the 220 kV high-voltage network at 12:48 p.m. As a result of the incident, the block was also disconnected from the 380 kV network due to faulty control mechanisms. This sudden drop in load meant that the system was no longer able to stabilize for its own needs. As a result of these events, the reactor was automatically shut down to avoid further safety risks and all four emergency diesel generators were started, which were necessary to maintain reactor safety. At 1:18 p.m. the 380 kV main grid was reconnected and the emergency diesel generators were switched off by 2:23 p.m. According to information from RWE, the system behaved according to its design, and at no point was there any increased risk to the population.
  • September 15, 2006 : While Block A was being revised, there was another faulty shutdown of the 380 kV network with a load shedding on internal demand . To prevent damage to the turbine of the secondary circuit, a TUSA (turbine shutdown) was carried out, which in turn necessitated a reactor shutdown .
  • April 4, 2011 : After a fire in a substation in Bürstadt (Bergstrasse), the switchover to the reserve network failed in two redundancies. The emergency diesel with the corresponding redundancies behaved as designed and supplied the nuclear area. The incident was classified in category N (normal message)

Other occurrences

Because the following occurrences were all from one source and not fully reported, the following occurrences cannot be clearly assigned to a block.

  • March 1994 : The motor of a main coolant pump burned inside the containment in Biblis A because a short-circuit had occurred due to a chisel forgotten in the pump during maintenance work. As a result, there was a dispute between the Hessian environment minister and the federal environment minister over the decommissioning of the reactor.
  • July 3, 1998 : Radiant spots ("hot spots") are discovered on an empty transport container for spent fuel elements. The radiation is 7500 times the permissible value.
  • July 11, 1998 : Two leaks were discovered in Block B on the secondary circuit.
  • January 6, 1999 : A secondary cooling system in the disconnected block B is radioactively contaminated by a defective heating pipe. The nuclear supervisory authority insists that RWE must first clarify the "damage mechanism" before unit B can be approached again.
  • August 28, 2002 : Error in the power supply of the emergency system. There was a "false excitation" of a relay and then a power failure in one of a total of four power supply lines of the emergency system. The Hessian Environment Minister appoints the management company's board of directors.
  • April 28, 2003 : The Hessian Environment Minister announced that the emergency cooling system has been inadequate since Biblis A was put into operation and does not correspond to the operating license. There was a risk of the reactor overheating in the event of an accident. The reactor was therefore temporarily shut down.
  • July 12, 2004 : Only half the emergency cooling system worked for over two hours.
  • October 16, 2006 : Unscheduled shutdown of blocks A and B due to dowel connections on pipe supports that were not set according to specifications. The special dowels had been retrofitted under the supervision of an expert to make the systems more earthquake-proof . Random checks showed that about 70% of the 20 cm long dowels did not have a red marking that was flush with the concrete wall. In January 2007 it was reported that the incorrectly installed special dowels should be replaced by longer dowels; in June it was announced that all 15,000 special anchors would be replaced. After the competent authorities had confirmed the completion of all anchor renovation work and the revision measures carried out in parallel, Unit B of the Biblis power plant resumed operation on December 1, 2007. According to a press release from RWE Power on February 9, 2008, the Hessian Ministry for the Environment, Rural Areas and Consumer Protection has given the approval to restart Block A. The prerequisite for this step was the successful completion of the anchor renovation and all revision measures. The multi-day measurement and commissioning program was then started in block A.

Investigation committee in the Hessian state parliament

In March 2014, the investigation committee 19/1 was set up in the Hessian state parliament to clarify what happened during the provisional closure in March 2011 and who was responsible for it. The final report was published on April 21, 2016.

Others

The Biblis nuclear power plant maintains partnerships with the Balakowo (Russia), Zaporischschja and Rivne (both Ukraine) nuclear power plants to exchange experiences.

Until the mid-1990s, no official abbreviation was used for the Biblis nuclear power plant, as is common with most other nuclear power plants. The abbreviation KKB was already assigned to the Brunsbüttel nuclear power plant and KWB was reserved for the planned nuclear power plant in Borken , Hesse . It was only after the project in Borken was finally abandoned in 1995 that the abbreviation for the Biblis nuclear power plant was used.

In the 1987 novel Die Wolke by writer Gudrun Pausewang , which tells of a fictitious reactor accident in Germany, the nuclear power plant in Biblis is mentioned in the foreword.

Film productions

See also

Web links

Commons : Biblis Nuclear Power Plant  - collection of images, videos and audio files

Individual evidence

  1. rwe.com press release from March 19, 2011
  2. rwe.com press release
  3. Nuclear power: RWE is suing against Biblis shutdown. In: The time . March 31, 2011, accessed June 16, 2015 .
  4. ^ Atomic moratorium: RWE wants to restart Biblis A. In: Focus Online . April 1, 2011, accessed June 16, 2015 .
  5. Hessian Administrative Court : Judgment of February 27, 2013. Az. 6 C 824 / 11.T, “Decommissioning of a nuclear power plant”. In: Hessenrecht Land Jurisdiction Database. Accessed June 2, 2020 (on the action for a declaratory judgment on Block A).
  6. Hessian Administrative Court : Judgment of February 27, 2013. Az. 6 C 825 / 11.T, “Decommissioning of a nuclear power plant”. In: Hessenrecht Land Jurisdiction Database. Retrieved on March 2, 2015 (on the action for a declaratory judgment on Block B).
  7. BVerwG : Decision of December 20, 2013. Az. 7 B 18.13. Retrieved on June 2, 2020 (on Biblis Block A).
  8. BVerwG : Decision of December 20, 2013. Az. 7 B 19.13. Retrieved on March 2, 2015 (on Biblis Block B).
  9. ^ Biblis judgment: Hessen-SPD calls for Puttrich's resignation. In: FAZ. March 27, 2013, accessed June 16, 2015 .
  10. a b The Committee of Inquiry 19/1. (No longer available online.) The President of the Hessian State Parliament, archived from the original on March 7, 2015 ; Retrieved on March 2, 2015 : “The commission of inquiry has the mandate to comprehensively clarify who is responsible for the illegal orders for the provisional decommissioning of the two nuclear power plant units in Biblis and which circumstances led to the unlawful decommissioning order of March 18, 2011. It must also be clarified whether the state government has truthfully and completely informed parliament and the public about these events. "
  11. Federal Network Agency will not order the reserve operation of a nuclear power plant
  12. RWE Power AG: Preparation of an application for decommissioning for the direct dismantling of the Biblis power plant May 11, 2012, accessed May 23, 2012
  13. Announcement about the project of RWE Power AG, Biblis power plant, 68647 Biblis, according to § 7 paragraph 3 of the Atomic Energy Act (AtG) of April 8, 2014, BAnz AT April 24, 2014 B12
  14. Biblis power plant uses approval - dismantling begins press release from RWE Power AG, June 1, 2017
  15. Martin Volkmer: Nuclear energy basic knowledge . KernEnergie Information Circle, Berlin June 2007, ISBN 3-926956-44-5 . Page 57
  16. Power Reactor Information System of the IAEA : "Germany, Federal Republic of: Nuclear Power Reactors" (English)
  17. Hans Werner Kilz and Jürgen Scherzer: Dregger is Reagan in Hessian . In: Der Spiegel . No. 33 , 1982, pp. 37 ( Online - Aug. 17, 1982 ).
  18. ^ The Biblis C nuclear power plant at the IAEA PRIS ( Memento from June 4, 2011 in the Internet Archive )
  19. ^ German Atomic Forum e. V .: Nuclear Energy - Current 2007 , Chapter Intermediate Storage / Transport . Berlin, September 2007.
  20. 500,000 euros per day. RWE does not restart Biblis. n-tv, June 16, 2011, accessed June 16, 2015 .
  21. Interview with Wolfgang Renneberg , former head of the Federal Atomic Energy Agency, from October 21, 2010
  22. RWE press release on the transfer of electricity volumes
  23. BMU press release on the transfer of electricity volumes from the Emsland power plant
  24. The clock for Biblis A is ticking. RWE fails in court. n-tv , February 27, 2008, accessed June 16, 2015 .
  25. Daniel Wetzel: Federal Court rejects longer nuclear power plants. In: The world . March 26, 2009, accessed June 16, 2015 .
  26. Joachim Wille: Biblis A nuclear power plant is being extended. In: Berliner Zeitung . May 11, 2010, accessed June 16, 2015 .
  27. Two unsuitable fuses found in the Biblis nuclear power plant In: wp.de , November 1, 2001, accessed on November 28, 2018.
  28. Shut down Biblis B - IPPNW takes legal action; September 13, 2005
  29. http://www.ippnw.de/presse/presse_2008/index.html?expand=2430&cHash=fbe88370d8
  30. Energy deal: Biblis nuclear power plant can run longer. In: Spiegel Online . August 4, 2010, accessed June 16, 2015 .
  31. fnp.de: State of Hessen expects the dismantling of Biblis to begin in 2016.  ( Page no longer available , search in web archivesInfo: The link was automatically marked as defective. Please check the link according to the instructions and then remove this notice.@1@ 2Template: Dead Link / www.fnp.de  
  32. Generator becomes a motor. (No longer available online.) In: Press release. Amprion , February 24, 2012, archived from the original on December 17, 2012 ; Retrieved September 29, 2012 .
  33. New tasks for Biblis Generator . In: energy spectrum . No. 03/03/2012 ( article online [accessed September 29, 2012]).
  34. RWE Power: Modernization and retrofitting of the KWB ( Memento from October 15, 2007 in the Internet Archive ) (PDF)
  35. Greenpeace risk remaining term - problems and weaknesses of the four oldest German nuclear power plants (PDF; 101 kB)
  36. Printed matter 16/394 (PDF; 80 kB): Answer of the Federal Government to a small request from the Greens, page 3
  37. http://www.taz.de/digitaz/2006/01/16/a0120.archiv/textdruck
  38. Biblis site: Monitoring of radioactivity ( Memento of December 17, 2012 in the Internet Archive )
  39. Nuclear power plants in the Federal Republic of Germany ( Memento from May 5, 2009 in the Internet Archive )
  40. 1987 annual report on special incidents in nuclear power plants ( Memento of January 17, 2012 in the Internet Archive ) (PDF; 990 kB), p. 14
  41. http://www.taz.de/digitaz/1988/12/05/a0020.archiv/textdruck
  42. http://www.taz.de/digitaz/1989/03/11/a0031.archiv/textdruck
  43. http://www.taz.de/digitaz/1988/12/19/a0018.archiv/textdruck
  44. Costs failed nuclear power plant projects: Billions in investments without income In: tagesschau.de , October 22, 2015, accessed on November 28, 2018.
  45. Overview of special incidents in nuclear power plants in the Federal Republic of Germany. (PDF) For the year 1989. (No longer available online.) Federal Ministry for the Environment, Nature Conservation and Nuclear Safety , 1989, p. 31 , archived from the original on January 23, 2012 ; Retrieved February 19, 2014 .
  46. Bernhard Lutz: Always broken. The Biblis nuclear power plant holds the record for incidents. In: The time . Zeitverlag Gerd Bucerius , March 9, 1990, accessed on February 19, 2014 .
  47. Incident in the Biblis A reactor In: taz.de , November 11, 1999, accessed on November 28, 2018.
  48. Biblis for two hours without emergency power ( Memento from June 2, 2016 in the Internet Archive )
  49. nuclear energy in Germany; Annual report 2006. Publisher: Deutsches Atomforum eV Page 24/25 Biblis A nuclear power plant; Information Circle KernEnergie; Printing: UbiaDruckKöln; ISSN  1611-9592
  50. BMU report (PDF; 681 kB) on fires in German nuclear power plants, page 31
  51. ^ Wall of flames on the monitor In: taz.de , March 7, 1994, accessed on November 28, 2018.
  52. Radiant container in the Biblis nuclear power plant In: taz.de , July 3, 1998, accessed on November 28, 2018.
  53. Cooling systems in the Biblis nuclear power plant leaked twice In: taz.de , July 11, 1998, accessed on November 28, 2018.
  54. Leak caused Biblis incident In: taz.de , January 23, 1999, accessed on November 28, 2018.
  55. Biblis under supervision In: taz.de , September 6, 2002, accessed on November 28, 2018.
  56. ^ "AKW Biblis is like Russian roulette" In: taz.de , April 28, 2003, accessed on November 28, 2018.
  57. Another incident in the incident reactor In: taz.de , July 15, 2004, accessed on November 28, 2018.
  58. http://www.djvhessen.de/Seiten/Nachrichten/2007/070314_01.htm  ( Page no longer available , search in web archivesInfo: The link was automatically marked as defective. Please check the link according to the instructions and then remove this notice.@1@ 2Template: Toter Link / www.djvhessen.de  
  59. RWE Power press release of December 2, 2007
  60. Minutes of the 7th plenary session. (PDF) (No longer available online.) Hessian State Parliament, March 13, 2014, archived from the original on April 2, 2015 ; accessed on March 2, 2015 .
  61. ^ Urgent motion by the SPD parliamentary group. (PDF) regarding the establishment of a committee of inquiry. In: Drucksache 19/193. Hessian State Parliament, March 13, 2014, accessed on March 2, 2015 .
  62. Printed matter 19/3429 (pdf 1.6 MB)
  63. Nuclear Power Plants in Germany: Operating Results 2009 ( Memento of the original from October 5, 2013 in the Internet Archive ) Info: The archive link was inserted automatically and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. @1@ 2Template: Webachiv / IABot / www.kernenergie.de
  64. 20 years of WANO partnership between Balakovo and Biblis nuclear power plants ( Memento from May 12, 2014 in the Internet Archive )