Autópálya M85

from Wikipedia, the free encyclopedia
Template: Infobox high-ranking road / maintenance / HU-M
M85-ös autópálya in Hungary
M85
 E65-HUN.svg
map
Course of the M 85
Basic data
Operator: Magyar Közút Nonprofit Zrt.
Overall length: 80 km
  of which in operation: 31.6 km
  of which under construction: 64.9 km

Megyék ( counties ):

Development condition: four lanes
(six lanes before Csorna)
M85 Enese1.JPG
M 85 at Enese
Course of the road
node (0)  Győr to BudapestM1 E60 E75
Roundabout Roundabout F85
Start of the road Motorway crossing
Junction (8th)  Rábapatona
Junction (9)  Enese , Bezi
Junction (16)  Kóny Rábcakapi F85
(17)  Kóny pihenőhely
Junction (21)  Csorna , diversion SopronF85
Template: AB / Maintenance / Empty Shared route with M86
node (23)  Csorna -kelet F86according to Mosonmagyaróvár
node (27)  Csorna-dél M86to Szombathely
Junction (32)  Csorna-nyugat, Farád
Gas station Rest stop (40)  Babóti pihenőhely
Junction (42)  Kapuvár , Babót
parking spot (40)  Fertőszentmiklósi pihenőhely
Junction (60)  Fertőszentmiklós , Röjtökmuzsaj
node (68)  M9to Kaposvár , Szeged
Junction (81)  Sopron -kelet, Nagycenk F84
bridge Kópháza F861
Junction (84)  Balf
Junction (87)  Sopron-észak, Fertőrákos
tunnel (90)  Vienna hill tunnel (780 m)
Junction (90)  Sopron nyugat F84
EU border crossing (94)  Border crossing Sopron ( HU ) - Klingenbach ( AT )
Austria Continue on  A3Vienna
  • Under construction
  • In planning
  • Autópálya M85 ( Hungarian for 'motorway M85') is a planned expressway ( Hungarian : Autóút ) in Hungary and part of the European route 65 . It begins in Győr and ends near Sopron on the state border with Austria . There it connects to the southeast motorway (A3). At Csorna it is to cross the M86 motorway .

    history

    The first 7 km long section near Enese was completed on December 21, 2011. The Kóny - Győr line was opened as a bypass from Enese on June 16, 2015. The new section from Kóny to Csorna -Süd was opened on September 9, 2015. On December 1, 2017, the construction companies were commissioned with the upgraded Csorna-West line to the Sopron / Fertőrákos junction. A total of 57.45 km of new line would have to be built from 2018. The 4.5 km long stretch from Csorna-Süd to Csorna-West would begin at the confluence of the M86 and connect to the M85 at Farád in the southern bypass of Csorna . The line was built from May 19, 2016 to December 15, 2017.

    Route approvals

    section length start of building Installation
    Győr - Enese 10.0 km June 2013 September 9, 2015
    Enese bypass 7.0 km July 20, 2009 December 21, 2011
    Enese - Csorna -Süd
    with a common section between Csorna-Süd and Ost with M86
    12.5 km June 2013 September 9, 2015
    Csorna South - Csorna West 4.5 km 19th May 2016 15th December 2017
    Csorna-West - Nagylózs 36.1 km March 6, 2018 2020 October
    Nagylózs - Sopron - Fertőrákos 21.8 km February 26, 2018 2020
    Fertőrákos - Sopron West
    and the border with 3.6 km north bypass Sopron
    7.6 km + 3.6 km 06/11/2019 2024

    expansion

    Route: Csorna – Pereszteg

    The environmental impact assessment procedure for the Csorna-Pereszteg section was completed in 2016 . The 38 km long route is to be built between 2017 and 2020.

    Route: Pereszteg – Sopron

    The 27 km long route will start in Pereszteg and end at the Sopron / Fertőrákos junction. Investigations into the first route variants were completed in 2000. The environmental impact assessment (EIA) procedure for the Pereszteg border section was completed on October 16, 2015 . The 27 km long route is to be built between 2017 and 2020.

    Sopron limit

    The 7.6 km long route will begin at the Sopron / Fertőrákos junction and connect with a northern bypass from Sopron to the south-east A3 motorway near Eisenstadt in Austria . The 3.6 km north-west bypass from Sopron is under construction: from the Sopron-North node M85 / B84 to Agendorfer Landstrasse. Under the Viennese hills a tunnel is to be built in the classic mining method - with a length of 780 m. The expressway is to be built up to km 92 + 950 by 2024, of which the 4-lane, temporary connection up to the border is to be expanded to main road 84 and today's 4-lane border road is to be modernized. In June 2019, the company was commissioned to carry out the work for 49.9 billion forints. Archaeological excavations have been ongoing on the route of the future M85 expressway to the border since spring 2019. From March 2020 , the earthworks required to build the tunnel were completed.

    Sections as a European route

    The Csorna bypass (triangle east-south) on the Autóút M85 is part of the E 65 .

    Traffic volume

    Average daily traffic on the motorway

    section DTV
    Győr (Cross M1 - Rábapatona) 19,786
    Csorna (Csorna-kelet - Csorna-dél) 18,833

    Paid routes

    The M85 in Hungary is almost completely chargeable.

    See also: toll in Hungary

    County-wide vignette

    From January 1, 2015, users of the M85 expressway can use a national e-sticker or the following county-wide vignettes:

    County Usable section
    FLAG-Gyor-Moson-Sopron-megye.svg Győr-Moson-Sopron at the M1 motorway junction to Sopron (full length)

    Web links

    Commons : M85 (Hungary)  - Collection of pictures, videos and audio files

    Individual evidence

    1. Gyorsforgalmi úton Győr és Csorna között (Hungarian) ( Memento of the original from October 3, 2015 in the Internet Archive ) Info: The archive link was automatically inserted and not yet checked. Please check the original and archive link according to the instructions and then remove this notice.  @1@ 2Template: Webachiv / IABot / nif.hu
    2. Ezek a cégek vihetik el Sopronig az M85-east (Hungarian)
    3. M85: átadták a csornai elkerülőt - fotók (Hungarian)
    4. Szeptember 9-én átadják a csornai elkerülőt - A város fellélegzik, Demjén Rózsival ünnepel (Hungarian)
    5. M85: átadták a csornai elkerülőt - fotók (Hungarian)
    6. M85-ös útépítés: letették az alapkövet Sopronnál (Hungarian)
    7. Ezek a cégek vihetik el Sopronig az M85-east (Hungarian)
    8. Pompás időzítéssel települtek munkagépek az M85-ös tervezett nyomvonalára Sopronnál (Hungarian)
    9. Kiderültek a Sopron gyorsforgalmi elérhetőségét célzó projekt részletei (Hungarian)
    10. Agreement M85 (Hungarian)
    11. Kiderültek a Sopron gyorsforgalmi elérhetőségét célzó projekt részletei (Hungarian)
    12. Megkezdődik az M85 gyorsforgalmi út Csorna II. Ütem - Pereszteg közötti szakasz előkészítése . Nemzeti Infrastruktúra ZRt .. Archived from the original on March 14, 2014. Info: The archive link was automatically inserted and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. Retrieved March 14, 2014. (Hungarian) @1@ 2Template: Webachiv / IABot / www.nif.hu
    13. ^ Motorway expansion with many question marks
    14. Egy engedély megvan - M85-ös: tisztul a pálya Sopronnál (Hungarian)
    15. FOLYTATÓDIK PERESZTEG-SOPRON-ORSZÁGHATÁR KÖZÖTTI SZAKASZ KIVITELEZÉSÉNEK ELŐKÉSZÍTÉSE . Nemzeti Infrastruktúra ZRt .. Archived from the original on October 29, 2013. Info: The archive link was automatically inserted and has not yet been checked. Please check the original and archive link according to the instructions and then remove this notice. Retrieved October 24, 2013. (Hungarian) @1@ 2Template: Webachiv / IABot / www.nif.hu
    16. Procurement of M85 (Hungarian)
    17. Miből áll az M85-ös? A meghosszabbított alagút (Hungarian)
    18. NIF_M85 tervezés kivitelezés_2018-09
    19. Kiderülle, kik építik meg az M85-ös alagútját (Hungarian)
    20. Látványosan halad az M85-ös építkezése - with picture gallery (Hungarian)
    21. Előkészítő munkák az M85-ös soproni alagútjánál! (Hungarian)
    22. Forgalomszámlálás - Az országos közutak 2018. Èvre vonatkozó keresztmetszeti forgalma (Report of the Federal Highway Research Institute.) .