List of power plants in Namibia
This is a list of the current and planned power plants in Namibia .
The energy of Namibia made solely by the state electric utility Namibia Power Corporation and its regional subsidiaries. The power supply in rural areas is still largely ensured by individually operated generators and solar energy .
A large part of the required electrical energy is obtained on the basis of an agreement mainly from Zimbabwe (150 MW) and from the South African electricity supplier Eskom as well as from Zambia . Numerous contracts expire by 2016, so that more power plants are to be expanded and newly built in their own country . Currently (as of December 2015) a maximum of 511 MW can be produced by own power plants. Between 1990 and 2009 Namibia imported an average of 48 percent of its electricity requirements, between 2010 and 2017 it was 38 percent.
The annual consumption in Namibia was 611 MW in 2015 , of which up to 80 percent can now be covered by our own power plants at peak times. The demand is to rise to 879 MW by 2020. The power supply is considered safe due to sufficient imports.
Current situation
All of southern Africa will face energy shortages for the next 15 years. The construction of the Grand Inga power plant in the Democratic Republic of the Congo could solve some of the bottleneck. The Namibian electricity supplier Nampower has already warned of bottlenecks and suggested a reduction in electricity consumption of at least 10%. The entire SADC is projected to have a financial requirement of 170 billion US dollars to build new power plants and electricity grids.
Power plants
KW name | Power in MW | Location | operator | status | Art | image |
---|---|---|---|---|---|---|
Old Renewable Hardap | 37-45.5 | at Mariental | Old Renawable Hardap | Commissioning in June 2019 | Photovoltaics | |
Anixas | 22.5 | Walvis Bay | NamPower | Commissioning August 2011 | diesel power | |
Arandis | 3 | Arandis | OLC Solar Energy | Commissioning June 2017 | Photovoltaics | |
Exterior sweeping | 5 | with exterior sweeping | InnoSun | in operation since the end of 2017 | Photovoltaics | |
Benguela Wind Power Demonstration Project | 0.0105 | Luderitz | u. a. University of Namibia | Commissioning in September 2017 | Wind energy | |
Ejuva I + II | 10 | Gobabis | Ejuva | Commissioning September 2018 | Photovoltaics | |
Greenam Keetmanshoop | 10 | Keetmanshoop | Greenam Electricity | 2018 | Photovoltaics | |
Greenam Mariental | 10 | Mariental | Greenam Electricity | Commissioning March 2018 | Photovoltaics | |
HopSol solar park Karibib | 5 | Caribib | HopSol Power Generation | Commissioning on June 9, 2017 | Photovoltaics | |
HopSol solar park Otjiwarongo | 5 | Otjiwarongo | HopSol Power Generation | Commissioning November 2015 | Photovoltaics | |
InnoSun Omburu | 4.5 | Omaruru | InnoSun | Commissioning May 2015 | Photovoltaics | |
Ombepo | 5 | Luderitz | InnoSun | Commissioning on August 3, 2017 | Wind power | |
Osona Plant | 5 | Okahandja | InnoSun | Commissioning August 2016 | Photovoltaics | |
Otjozondjupa Solar Park | 5 | Grootfontein | HopSol Power Generation | Commissioning July 2016 | Photovoltaics | |
Outapi Solar Plant | 5 | Outapi | Camelthorn Business Ventures | Commissioning July 2018 | Photovoltaics | |
Paratus | 20th | Walvis Bay | NamPower | Thermal power from fossil fuels | ||
Rosh Pinah PV | 5 | Rosh Pinah | AEE Power | Commissioning August 2017 | Photovoltaics | |
Ruacana | 247 | Ruacana , on the Kunene | NamPower | General overhaul completed in May 2014 | Hydropower | |
Ruacana (extension) |
92 | Ruacana, on the Kunene | NamPower | Commissioning in March 2012 | Hydropower | |
Trekkopje | 5.78 | Trekkopje | Enertronica Group | Commissioning August 2018 | Photovoltaics | |
Trekkopje Solar Project | 5 | Arandis | SertumEnergy Namibia | Commissioning October 2019 | Photovoltaics | |
Van Eck | 120 | Windhoek | NamPower | General overhaul completed in mid-2015 | Coal power | |
TOTAL | 628.78-635.28 |
Future power plants
Under construction
KW name | Power in MW | Location | operator | status | Art |
---|---|---|---|---|---|
Ruacana (extension) |
15th | Ruacana , on the Kunene | NamPower | Commissioning was planned for 2014 | Hydropower |
Diaz wind farm | 44 | near Lüderitz | United Africa , Sojitz , KOMIPO | The start of construction was planned for the end of 2012; Preparations completed in June 2017; Start of construction December 2017 | Wind power |
OLC Tsumeb | 6.4 | at Tsumeb | OLC Solar Energy | Start of construction in early 2017 | Photovoltaics |
TOTAL | 70.4 |
Planned
KW name | Power in MW | Location | operator | status | Art |
---|---|---|---|---|---|
Agrekko | 150 | Walvis Bay | Agrekko | planned | Diesel power |
Anixas II | 50 | Walvis Bay | Nampower | Commissioning planned for March 2021 | Diesel power |
Arandis Power | 120 | east of Arandis | Construction will start around the end of 2020 | Heavy fuel oil power plant | |
Arandis | 300 | at Arandis | NamPower | first planning published in November 2015 [outdated] | Solar heating |
Baynes | 600 | Baynesberge , the Kunene | NamPower and Angolan partner | Planned start of construction in 2021, commissioning in 2025 | Hydropower |
Divundu | 20th | Divunde , on the Okavango | NamPower | planned | Hydropower |
Orange | 80-200 | Orange | planned together with South Africa | Hydropower | |
HopSol solar park Khorixas | 1 | at Khorixas | HopSol Power Generation | Start of construction planned for October 2015 [outdated] | Photovoltaics |
HopSol solar park Otavi | 2 | at Otavi | HopSol Power Generation | Start of construction planned for October 2015 [outdated] | Photovoltaics |
HopSol solar park Outjo | 2 | at Outjo | HopSol Power Generation | Start of construction planned for October 2015 [outdated] | Photovoltaics |
HopSol solar park Tsumeb | 5 | at Tsumeb | HopSol Power Generation | Start of construction planned for October 2015 [outdated] | Photovoltaics |
InnoSun restricted area | 150-500 | in the restricted area national park | InnoSun | Start of construction planned for 2016 [outdated] | wind |
Kudu gas field | 800 | Oranjemund | NamPower (cooperation with Gazprom , NAMCOR , Tullow Oil ) |
Commissioning was planned for 2017/2018. In September 2015, further planning was discontinued due to a cost explosion. Planning resumed in September 2016. |
Gas power |
unknown | unknown | Erongo region | planned for 2018 [obsolete] | Nuclear power | |
Lüderitz Wind | 40 | near Lüderitz | Nampower | Commissioning planned for 2022 | Wind energy |
Omburu II | 20th | at Omaruru | Nampower | Commissioning planned for 2020 | Photovoltaics |
Otjikoto biomass | 40 | at Tsumeb | Nampower | Commissioning planned for 2020 | Biomass power plant |
Thermal power station coast | 250 | at Walvis Bay | Nampower | Commissioning planned for 2016 [obsolete] [obsolete] | Thermal power plant |
Trekkopje Solar Project (extension) |
22nd | Arandis | SertumEnergy Namibia | Start of construction planned for 2017 | Photovoltaics |
Otjiwarongo | 40 | Otjiwarongo | NamPower | Construction announced in May 2017 | Bioenergy |
Otavi | 20th | Otavi | NamPower | Construction announced in May 2017 | Bioenergy |
Arandis | 150 | Arandis | NamPower | Construction announced in May 2017 | Solar heat |
unknown | 20th | Rehoboth or Gobabis | IPP (NamPower) | Photovoltaics | |
unknown | 50 | Luderitz | IPP (NamPower) | Wind energy |
Set plans
KW name | Power in MW | Location | operator | status | Art |
---|---|---|---|---|---|
Arandis | up to 800 | at Arandis | The start of construction was planned for 2012, further planning was stopped in March 2013, and planning was discontinued in November 2015 | Coal power | |
Greentower | 400 | at Arandis | originally planned for 2012 | Updraft power plant | |
Sitentu Power Plant | 900 | at Walvis Bay | Commissioning was planned for 2015 [out of date] | Combined gas and steam power | |
Xaris power plant | 250 | Dune 7 , at Walvis Bay | Xaris Energy Namibia |
Commissioning was planned for 2016; Government made plans due to cost explosion in May 2015 completed a new recording of the project in January 2016 and implementation to 2018 planned; abandoned all planning in February 2018. |
Gas power |
Web links
- Ministry of Mines and Energy (English)
- Namibia Power Corporation (NamPower )
- Erongo RED (English)
- CENORED (English)
- NoRED (English)
Individual evidence
- ↑ More electricity for Angola. In: Allgemeine Zeitung. August 9, 2011.
- ↑ Speech by Kornelia Shilunga, Vice Minister for Energy, at the opening of the photovoltaic system near Mariental, June 20, 2019.
- ↑ January 19, 2016 - Morning News. Hitradio Namibia, January 19, 2016.
- ↑ Media Release, Ministry of Mines & Energy of the Republic of Namibia, December 14, 2015
- ↑ Anixas power plant supplies electricity . Allgemeine Zeitung, August 24, 2011
- ^ OLC Solar energy project for Arandis. Confidenté, December 1, 2016.
- ↑ Researchers contemplate wind power in Lüderitz. The Namibia, August 5, 2016, p. 23
- ↑ Two solar plants opened in Namibia. Engineering News, August 23, 2018.
- ↑ HopSol project page , accessed on November 25, 2016
- ↑ Solar power from Omaruru. Allgemeine Zeitung, January 15, 2014 ( Memento from January 17, 2014 in the Internet Archive )
- ^ Rapid progress on new solar plants. The Namibian, May 17, 2016.
- ↑ Soon 90 MW more
- ^ Bank Windhoek finances 5, 78 MW Solar Plant. Bank Windhoek, September 26, 2018.
- ↑ Work starts on new solar farm near Arandis. The Namibian, May 19, 2016.
- ^ Project Information - UAG Diaz Wind Farm. World Bank, 2012. Retrieved March 12, 2015
- ↑ Third diesel power plant for Walvis Bay. Allgemeine Zeitung, November 1, 2013 ( Memento of November 12, 2013 in the Internet Archive ) Retrieved on November 12, 2013
- ^ Arandis Power responds to environmental concerns. New Era, February 13, 2020.
- ↑ "Green" option suggested. Allgemeine Zeitung, June 15, 2016. ( Memento from June 15, 2016 in the Internet Archive )
- ^ Namibia, Angola to develop cross-border Baynes hydroelectric dam. Construction Review, March 20, 2020.
- ↑ Further projects for power generation in Namibia in planning or under construction, Allgemeine Zeitung, November 15, 2010
- ↑ a b c d Cenored bets big on solar to avoid power crisis. The Namibian, September 16, 2015 ( Memento of March 10, 2016 in the Internet Archive )
- ↑ Kudu Gas
- ↑ Kudugas Project Before Change, Allgemeine Zeitung, December 18, 2009 ( Memento from February 21, 2013 in the web archive archive.today )
- ↑ Kudugas instead of coal. Allgemeine Zeitung, March 13, 2013 Retrieved March 14, 2013
- ^ Why finance is against Kudu. The Namibian, September 21, 2015 ( Memento of October 3, 2015 in the Internet Archive )
- ↑ Namibia: Nation Embarks On Nuclear Policy, allAfrica.com, January 5, 2011
- ↑ Fact Sheet Otjikoto Biomass Power Station. Nampower. Retrieved July 22, 2020.
- ↑ 4/16/2014 morning news. Hitradio Namibia, April 16, 2014 ( memento from April 16, 2014 in the web archive archive.today ) accessed on April 16, 2014
- ↑ Work starts on new solar farm near Arandis. The Namibian, May 19, 2016.
- ↑ a b c Namibia to build three plants to boost electricity security. The Namibian, May 2, 2017. (English)
- ↑ Hahn & Hahn is planning two solar towers
- ↑ Gigantic power plant planned. Allgemeine Zeitung, August 9, 2012
- ↑ Official website of the Walvis Bay Power Plant Project (English)
- ^ Gas-powered electricity plant for Walvis Bay. The Namibian, March 18, 2015. Retrieved March 18, 2015